14
4.1 Introduction
Kitchen/Utility models are supplied fully
assembled in a carton.
Boiler House models are supplied in two
cartons, one containing the boiler and
the other the burner and dual thermostat
(26/36, 36/46 only).
4.2 Boiler location
The boiler must stand on a firm and level
surface. The boiler base temperature
is less than 50°C. No special hearth is
required for Kitchen/Utility models. Boiler
House models
must
stand on a non
combustible surface.
Sufficient clearance
must
be
allowed
at the front of the boiler to remove the
burner and baffles for servicing.
Boiler House models -
Sufficient
clearance
must
be allowed above the
boiler to replace the boiler thermostat/
overheat thermostat.
Kitchen/Utility models -
Once the boiler
has been installed, a permanent worktop
may be fitted over it as access to the top
of the boiler is no longer required after
installation.
System models - A removable section
of worktop above the boiler is required
to provide access for servicing.
4.3 Preparation for Installation
Kitchen/Utility models:
1. Carefully remove the packaging from
the boiler and remove it from the
transit pallet.
2. Pull the front panel forward at the
top to disengage the fixing clips then
lift it up and off the boiler. Remove
the literature packs. Give the User
Information pack to the householder.
3. Lift off the case top panel(s) and
remove the water connecting fittings.
Boiler House models:
1. The Boiler House model comes
in two separate cartons, one
containing the boiler and the other
containing the burner and drain
trap. The dual thermostat and flow
pipe are also included with the
burner for 26/36, 36/46 models.
2. Carefully remove the packaging from
the boiler and unpack the carton
containing the remaining items.
4.4 Installing the Boiler
1. Having decided upon the position of
the boiler and type of flue, prepare
the wall as described in Section 9.
Ensure that the flue terminal position
complies with the necessary
clearances.
2. Make the water connections as
described in Section 5.
If access will be restricted, make
any connections to the boiler before
placing it in its final position.
Refer to Section 7 if the boiler is to
be used on a sealed system.
If using a balanced flue system - Install
the balanced flue system before
connecting the heating system pipework
to the boiler. Once the flue system
is fitted then complete the water
connections and fill the heating system.
3. Ensure the requirements are met
for the disposal of condensate as
described in Section 6.
4. Connect the power supply as
described in Section 8.
5. Connect the flue and ensure there is
an adequate air supply as described
in Section 9.
4.5 Regulations Compliance
Installation of a Grant VORTEx Pro boiler
must be in accordance with the following
recommendations:-
•
Building Regulations for England and
Wales, and the Building Standards for
Scotland issued by the Department
of the Environment and any local
Byelaws which you must check with
the local authority for the area.
Boiler Installation
Information
4
Boiler Installation Information
NOTE
!
•
Model and local Water Undertaking
Byelaws.
•
Applicable Control of Pollution
Regulations.
•
The following OFTEC requirements:-
- OFS T100 Polythene oil storage
tanks for distillate fuels.
- OFS T200 Fuel oil storage tanks
and tank bunds for use with
distillate fuels, lubrication oils and
waste oils.
Further information may be obtained from
the OFTEC Technical Book 3 (Installation
requirements for oil storage tanks) and
OFTEC Technical Book 4 (Installation
requirements for oil fired boilers).
The installation should also be in
accordance with the latest edition of
the following British Standard Codes of
Practice:-
•
BS 715 Metal flue pipes, fittings,
terminals and accessories.
•
BS 799:5 Oil storage tanks.
•
BS 1181 Clay flue linings and flue
terminals.
•
BS 4543:3 Factory made insulated
chimneys for oil fired appliances.
•
BS 4876 Performance requirements
for oil burning appliances.
•
BS 5410:1 Code of Practice for oil
firing appliances.
•
BS 5449 Forced circulation hot water
systems.
•
BS 7593 Code of Practice for
treatment of water in heating systems.
•
BS 7671 Requirements for electrical
installations, IEE Wiring Regulations.
Failure to install and commission
appliances correctly may invalidate
the boiler warranty.
Before starting any work on the
boiler, or fuel supply please read the
health and safety information given in
Section 14.
NOTE
!
WARNING
!
NOTE
!