background image

31 

 
 
 
 

 

 
 
 

Granby  Furnaces Inc.  manufactures a full line of oil and gas-fired 
boilers in its 70,000 square feet facility. Granby products are sold 
across  Canada  and  the  United  States  through  a  distribution 
network. 

 

Our  team  of  engineers,  designers  and  technicians  continually 
research  and  develop  products  to  go  beyond  the  demanding 
specifications of today’s certifications. 

 
 
 
 

 

 
 
 
 

Thank you 

Thank you 

Thank you 

Thank you for choosing Granby

for choosing Granby

for choosing Granby

for choosing Granby....    

Содержание B*C-3 sections

Страница 1: ...IFFER FROM THIS MANUAL Please read the manual in its entirety before beginning installation This manual must be kept with the boiler for future reference GRANBY FURNACES INC PO Box 637 12118 Hwy 209 P...

Страница 2: ...MATION 13 7 0 FUEL SYSTEM 14 8 0 ACCESSORY INSTALLATION 15 9 0 BURNER INSTALLATION SETTING 16 10 0 TECHNICAL INFORMATION 20 11 0 BOILER START UP OPERATION 21 11 1 START UP PROCEDURE 21 11 2 L7248 HONE...

Страница 3: ...AMPER WITH THE BOILER OR CONTROLS CALL A QUALIFIED BURNER TECHNICIAN DO NOT STORE OR USE GASOLINE OR OTHER FLAMMABLE VAPOURS AND LIQUIDS IN THE VICINITY OF THIS UNIT OR ANY OTHER APPLIANCE IMPORTANT T...

Страница 4: ...local codes and CSA B139 Consult local fire codes for required clearances Connections to chimney must be made with the proper gauge thickness and diameter of fluepipe as required by CSA B139 CLEARANCE...

Страница 5: ...LACEMENT LEVELING OF THE UNIT The boiler should be located on firm foundation in an easily accessible area that meets the previously discussed clearances and air requirements In situations where the f...

Страница 6: ...will be used to level the boiler Screw the 4 mm jacket affixing screw to the frame rail from the top down Both the bolt and affixing screw will be located on the same end of the frame rail The frame r...

Страница 7: ...ND BACK PANEL ATTACHMENT Affix panel mounting nuts to the rear of the tie rods Mount the side panels by placing the panel over the frame rail so that the hole in the bottom lip of the panel fits direc...

Страница 8: ...to insert the sensor The sensor must be fully inserted to the bottom of the well STEP 7 TOP AND FRONT PANEL ATTACHMENT Affix the top panel by placing the holes located on the underside of the panel ov...

Страница 9: ...ast iron system If the conversion is from a high volume system a bypass loop must be installed Manual shut off valves must be installed on both the supply line and on the boiler bypass loop ASME Boile...

Страница 10: ...eratures above 200 F and within limits advised by the manufacturer The pump must not be operated unless the system has been bled of all air and completely filled with water Recommended locations for t...

Страница 11: ...2 A typical installation with no domestic hot water and with a by pass loop installed Figure 3 A typical installation with domestic hot water supplied by an indirect heater and with no by pass loop i...

Страница 12: ...his manual and only by qualified individuals The boiler and burner should only be operated on 120 Vac Field connections should be properly sized and protected with a minimum 15A fuse or circuit breake...

Страница 13: ...ng zone Typical wiring for line voltage oil burner with Fuel Smart HydroStat 3250 and one heating zone Insert sensor ALL THE WAY into well through the knockout A or B you have chosen WARNING For Canad...

Страница 14: ...nnection The chimney connector should be at least 24 gauge metal be properly supported and be free of as many 90 degree turns as possible The distance between the boiler and the chimney depends on whe...

Страница 15: ...return fuel line may be used on inside installations where the tank level is below the level of the burner The return line must be equal in diameter to the suction line The minimum size for the oil l...

Страница 16: ...Not applicable for Direct Vent systems Field Controls Model WMO 1 Manual Reset Switch Operation Blocked vent switches are flue gas safety devices for detecting spillage of flue gases due to a blocked...

Страница 17: ...heat 3 Once the heating system has started the blocked vent switch should shut down the burner within 10 minutes or sooner 4 Once the system has cooled the blocked vent switch can manually be reset 5...

Страница 18: ...y setting no PLUG plug SET BURNER FOR EFFICIENT OPERATION BURNER SETTING Use burner settings in the table on page 20 or operating decal as a guide to set burner particularly for nozzle changes Those s...

Страница 19: ...03 w c draft pressure at the breech sampling hole The draft regulator s adjustments should be made after boiler has been running under heating mode for at least 5 minutes All your tests must be done...

Страница 20: ...nd adjustment on the burner to reduce your CO2 reading by 1 You now have a perfect slight trace of smoke Relation between of CO2 and O2 CO2 O2 Excess Air 13 5 2 6 15 0 13 0 3 3 20 0 12 5 4 0 25 0 12 0...

Страница 21: ...S YES YES YES YES AFUE 87 4 87 4 87 3 87 1 87 4 87 5 CO2 13 13 13 13 13 13 In the Unit Model number is specific information of the product for administration only 3H for Honeywell control L7248 high l...

Страница 22: ...te operation The use of accurate instruments is necessary to achieve maximum efficiency and lowest fuel costs Adjust the thermostat to manufacturer s instruction Place this manual the control manual a...

Страница 23: ...ent disconnect thermostat short T T Boiler starts check wiring and thermostat 120 V a c at B1 B2 If no replace control If yes check burner and wiring Boiler is not house is cold Display is ON 120 V a...

Страница 24: ...ndirect switch DIAGNOSTIC LEDs and Test Button B JUMPER Indicator Light Heat Call A High temp limit setting 100F 220F Factory set at 190F D Economy Dial OFF or LO 1 2 3 4 5 and HI C Low Temperature Li...

Страница 25: ...24...

Страница 26: ...25 Trouble Shouting the HydroStat 3250...

Страница 27: ...tween the furnace and the chimney base If this is not sufficient consider cutting or removing some flue baffles in the furnace BE AWARE THAT REMOVING BAFFLES REDUCES THE UNIT EFFICIENCY AND A MODIFIED...

Страница 28: ...the smoke hood C Baffles cleaning C access door A B C Replace insulation on the rear section and smoke hood Replace swing door and tighten bolts Refit the front casing 12 2 BURNER NOTES Your burner ma...

Страница 29: ...28 13 0 EXPLODED PARTS VIEW Exploded Parts View...

Страница 30: ...T M8 24 FRONT DOOR REFRACTORY F WASHER A8 4 25 27 29 2ND PASS RETARDERS G SETSCREW M5 x 15 26 28 3RD PASS RETARDERS H NUT M6 30 DELIVERY STUB PIPE J WASHER A6 4 31 RETURN STUB PIPE K STUD M6 x 22 44 B...

Страница 31: ...TS Size of unit Btu h Nozzle Oil Pressure psi Chimney size ____________ Direct vent system DVS _________ Burner adjustments RIELLO F3___ BF3___ RIELLO F5___ BF5___ RIELLO F10____ Turbulator Air Gate S...

Страница 32: ...ss Canada and the United States through a distribution network Our team of engineers designers and technicians continually research and develop products to go beyond the demanding specifications of to...

Отзывы: