402-INST-UK-003 v1.1
–
11 Dec 2020
Need assistance? +44 (0)1379 658300 [email protected]
Page 9 of 12
Installation Procedure
Prior to commencing installation, photographs of the fully weathered upstand and surrounding area must be taken
and retained for future reference.
Step 1
Remove all packaging from the product including polyfoam glass protection and low tack tape.
When removing the packaging, try to keep it intact as much as possible, so that after installation it can be re-used to
protect the product until project completion and final handover.
Gently prise all of the upstand fixing clip on covers off the framework drip legs.
Figure 5 - Clip on cover
Step 2
Apply two large lines of silicone (supplied in the installation kit) to the top of the upstand. The two lines of silicone need to be
approximately 20 mm and 40 mm in from the outside face of the upstand.
Figure 6
–
Silicone placement
Step 3
Fit the chosen lifting equipment to the product sections and check that it is secure.
Section by section, carefully lift the product to the installation site (roof) using strops underneath the wooden build frame/bocks.
This is to ensure that the build frame/blocks do not separate from the product during the lift.