INSTALLATION
IMPORTANT:
When installing ECO 190 follow these instructions:
1) Turn off the electricity before opening the unit
2) Install an air tight water trap on a non-freezing location
to compensate for the fan pressure.
3) The height of the water trap must be at least 50 mm.
4) Make sure that the drain flows downwards all the way
from the unit.
5) Pour 1 liter water into the drip tray of the unit to verify
that it is drained properly. Before each heating season
make sure that the drain is filled with water.
6) If freezing of the water trap occurs, it is necessary to
install a thermostat and electrical heater to prevent
freezing when the temperature drops below +2 °C.
7) Air flow adjustments must be made on both supply and
exhaust air sides before use of the machine. It is
important supply and exhaust air volumes are balanced.
8) It is recommended to keep the ducts closed until the unit
is started and the system is adjusted.
Above instructions must be followed. If the condensate
drain is not made according to this instruction, Genvex can
not be made responsible for any additional damages, which
have nothing to do with the Genvex unit.
ECO 190 CS/CL is intended for mounting on the ceiling
with special brackets, which is delivered together with
the ventilation unit (see photos).
Important: ECO 190 can only be installed horizontally.
1. Position the ceiling brackets according to the size of the
ventilation unit and mount with a total of 6 screws
capable of taking the entire weight of the unit.
2. Slide the ventilation unit with the preinstalled flanges
onto the ceiling brackets.
3. Finish the installation by installing a screw in the fixation
hole to ensure that the ventilation unit cannot move
out of the ceiling bracket.
ECO 190 is intended for mounting flat on a plain vibration-
free surface. Standard configuration is "right", which means
that supply and extract air from the house living room areas
are connected to the right side of the ventilation unit (note:
controller facing towards you). Stickers on the ventilation
unit indicate how to connect the ductwork.
PLEASE BE AWARE that project specific models can be
configured left - if so the stickers will indicate how to
connect ductwork.
1.
3.
On a "right" configured model the condensate drain and
syphon is connected to the left side of the ventilation unit
(i.e. on the fresh air and discharge side of the unit). The
condesate drain on the right hand side will be plugged and
is not in use.
Space necessary for installation recommended is machine
size including br 20 cm all around the unit.
100 cm free space is recommended in front of PCB to be
able to connect sensors and for service.
A minimum of 160 cm below the machine is recommended
for filter extract.
Please consider space required for siphon/condensate
drain when planning the installation of ECO 190.
2.
Information on how to configure a "right" unit to a
"left" unit on site can be aquired by contacting your
Genvex sales representative.
3