Entellisys Low Voltage Switchgear
Chapter 2. Receiving, Handling, and Storage
Fig. 2-6. Method of rolling equipment into place
7.
While carefully pushing the switchgear to its final site
position, the rollers that are freed from the rear of the
switchgear are then repositioned at the forward end.
This procedure should be continued until the
switchgear is in its final location. See
Fig.
2-6.
8.
When the switchgear is in its final position, remove all
lag bolts holding the shipping skids to the switchgear
line-up.
9.
Insert the tines of the forklift at one end of the line-up,
raise slightly, and remove the loose rollers.
10.
Lower the end of the gear carefully to the floor.
11.
Raise the other end of the line-up slightly and remove
the remaining roller at that end.
Jacks
Jacks may be used in place of forklifts to raise and lower
switchgear.
1.
Place a jack under the front and rear corners of one end
of the line-up.
CAUTION:
Do not place jacks in any other location other
than the front and rear corners of the switchgear. Doing so
may result in serious damage to the switchgear equipment.
ATTENTION:
Il ne faut pas placer de vérins en aucun
endroit autre que les coins avants et arrières du dispositif
de commutation. L’équipement peut être sérieusement
endommagé si l’on ne respecte pas cette directive.
2.
Raise the switchgear evenly and just enough to position
a roller beneath the equipment. Gently lower the
switchgear onto the roller. Repeat the procedure at the
opposite end of the switchgear, raising the gear far
enough to place the appropriate number of rollers under
the skids, spacing them evenly across the width of the
line-up. Gently lower the gear onto the rollers.
3.
While carefully pushing the switchgear to its final site
position, the rollers that are freed from the rear of the
switchgear are then repositioned at the forward end.
This procedure should be continued until the switchgear
is in its final location.
4.
When the switchgear is in its final position, remove all
lag bolts holding the shipping skids to the switchgear
line-up.
5.
Place one jack at each corner, front and rear, of the
switchgear. Carefully raise the line-up evenly and
remove the rollers and the shipping skids. Evenly lower
the line-up to the floor and remove the jacks.