7 OPERATION
START UP AND COMMISSIONING
A GE GLOBAL SERVICES FIELD ENGINEER must perform start-up and
commissioning of the UPS. Please Contact GE. Global Services at least
two weeks prior to schedule start-up and commissioning at 1-800-637-
1738, or by E-mail at
This symbol refers to the operations of a parallel system.
NOTE !
Verify for correct input/output cabling before connecting
Utility
to the
UPS.
Open only the front door, do not remove any panels.
Check after every step for correct reaction of the UPS (LED’s on the
panel), and correct voltage and current measurements, before you
proceed to the next step.
NOTE !
All operations (including start-up, shutdown, removing/adding a unit
from/to a Parallel System) MUST BE PERFORMED with
eBoost™ Operation
Mode
DISABLED.
Find on the following pages the descriptions of the various procedures of start-up and
shutdown for
UPS single
and
UPS Parallel System
,
divided into the following principal
chapters:
7.1
PROCEDURES FOR SINGLE
SG Series 750
&
SG Series 750 T12
7.2 PROCEDURES
FOR
SG Series 750
&
SG Series 750 T12
PARALLEL SYSTEM