6.0 ADJUSTMENTS
6.4 Main PCB Calibration
The Main PCB must be calibrated when replaced.To calibrate the PCB use the Calibration
fixture GBC p/n 1700407 and follow the calibration procedure outlined below. Calibration must
be performed with the new board installed in the machine.
Tools needed:
•
VOM with clips on test leads
•
Calibration Fixture GBC p/n 1700407
•
Precision screw driver
•
Infrared Temperature Sensor (Non Contact Thermometer)
Calibration Procedure
1. Calibration must be performed when laminator is cold.
2. Remove center shield to gain access to Main PCB.
3. Locate and preset the trim pots as follows.
a. Turn SV-1 and SV2 trim pots fully counter clockwise until you hear a clicking noise.
b. Turn SV-1 trim pot clockwise 5 full turns.
c. Tum SV-2 trim pot clockwise 10 full turns.
4. Disconnect temperature sensor from Main PCB and connect calibration fixture ( GBC p/n
1700407) in its place.
5. Disconnect the blue thermostat wire from the PCB.
6. Set VOM to measure DC voltage.
7. Locate test points on PCB and connect clip on leads from VOM to test points (refer to wiring
diagram in Section 5.0)
8. Locate the slide switch on the Main PCB and select the 'I' position. This is the calibrate
position.
9. Plug the laminator into a suitable 120V 60 Hz outlet.
10. Turn laminator power switch to the 'on' position.
11. Select SVl on the calibration fixture. Adjust SVl on the main PCB until you read
+13.7 VDC on the Multimeter. ( If you show -VDC on SVl you must show -VDC on SV2)
12. Select SV2 (DS 400,1200) setting on the calibration fixture. Adjust SV2 on the main PCB
until you read + 7. 92/+ 7. 93 VDC on the Multimeter.
13. Confirm the settings are correct by switching between SVl and SV2 on the Calibration
fixture and looking at the measured DC voltage on the VOM.
14. Switch the laminator to the "Off' position.
15. Move the slide switch to the 'No' position.
16. Disconnect the calibration fixture and reconnect the heat sensor to the PCB.
17. Disconnect VOM.
18. Re-attach blue thermostat lead.
14. Re-install center shield.
Содержание Docuseal 2700
Страница 24: ...DOC 2700 Parts List GBC IS AN ACCO BRANDS COMPANY...
Страница 27: ...S O PARTS Figure 8 2...
Страница 29: ...8 0 PARTS Figure 8 3 I I Is l...
Страница 32: ...S O PARTS Figure 8 5...
Страница 34: ...8 0 PARTS Figure 8 6 PIN 638001907 Ribbon Cable From Display P C B To Main P C B...