15
Installation:
1.
Using the drilling template mark the position of
the screws on the ceiling.
2.
Drill 4 holes Ø 8 mm for the wall plugs. Push the
plugs flush with the ceiling (Fig. 19).
3.
Turn two screws to a 10 mm gap. Both screws
are placed in a position, in which at a later stage
of the installation the key-holes of the suppor-
ting frame are found (namely front left and back
right from the control panel of the hood).
4.
Place the hood on a suitable base. Connect the
air outlet pipe to the hood.
5.
Screw the support frame to the hood with
4 screws. The marking “FRONT” must be on the
same side as the control panel (Fig. 20).
Ventilation ducts LK 590-020/030/021/031
only:
the enclosed extension module should be
mounted on top of the support frame. Follow the
above instructions for mounting the support
frame and hood.
346
200
Fig. 19
Fig. 20
Note:
the extractor hood is to be installed to a kitchen
ceiling or suspended ceiling. Ensure that the
ceiling is capable of providing a firm hold for a
maximum weight of hood and accessories of 60 kg.
Before marking the securing holes, make sure that
no electricity wires or water pipes or other wires/
pipes are laid at the drilling points in the ceiling.
Before installation check the enclosed wall plugs
and screws are suitable for your ceiling. If neces-
sary use special wall plugs.