GABRIEL KERAMIK AB
8
3
3a
100 mm
6
4
5
6
Assembly
Set the outer ring (3) with mortar.
Seal/insulate between the
firebox blocks.
Set the outer ring (3a) with mortar.
Be aware of the soot hole
dimension (ø100 mm
)
Level vertically and horizontally.
For a better joint, wipe
the contact surfaces with
a squeezed sponge.
Set the firebox block (6) with
mortar.
The firebox block must not touch
the outer rings (the firebox block
must be allowed to expand freely
without affecting the outer ring).
Seal with insulation at the front
edge of the U-formed blocks. Make
sure the soot hole is min. 100 mm.
Level vertically and horizontally.
Check the height, see page 5.
Make sure that no mortar
falls between the firebox
block and the outer ring
Insulation
All manuals and user guides at all-guides.com