background image

©2010 FFS 000-0309 Rev A

Figure 2: System Board Fastener Locations

Install New System Board

1.  Gently slide the board into the enclosure so that 

the communication ports are aligned with the 

proper holes in the enclosure. Gently push the 

board down so that the communication ports 

slide into the holes. Then push the board into the 

enclosure so that it is fully seated. 

2.  Tighten the two screws on the left hand side of the 

power supply (1 and 2 on Figure 2). 

3.  Install the long standoff in the bottom left hand 

corner and the short standoff in the top right hand 

corner (3 and 4 in Figure 2).

4.  Install one screw with lock washer in the bottom 

right hand corner (5 in Figure 2).

5.  Place the intrinsically safe shield and the ground 

strap over the potted area so that the hole is 

aligned with the hole in the short standoff and 

fasten with the remaining screw with lock washer 

(4 in Figure 2). The tab of the ground strap must 

be inserted between the display and the display 

support during reassembly. Ensure the tab of the 

ground strap is pushed into the crook of the display 

mount and not in contact with the glass of the 

display.

Note;  Units will be furnished with the IS shield and ground 

strap installed. 

6.  Connect power, relay and probe plugs to the proper 

receptacles.

7.  Connect any communication cables or USB sticks 

in use.

8.  Apply power to the unit.
9.  Upload any saved set-up, registration or database 

files as needed (TSA upgrade tool: select the tab 

and then click restore).