Each heater is equipped with two hi-temperature 12 gauge
silicone lead wires and a ground termination.  

Make sure

power source conforms to the heater requirements.  Use
only Fostoria quartz tubes. 

 

a.  Insert quartz tube in the “L”-shaped slots in heater

housing. 

 

b.  Remove first hex nut from each of the threaded studs

on the quartz tube. 

 

c.  Place ring terminals (attached to the wire leads) on

the threaded studs, replace hex nuts and 

tighten

securely

 

d.  Remove protective white film from one or both end

caps. 

 

e. 

Assemble both end caps to housing using the (4)
screws provided in hardware package.  For assembly
views refer to items 6 and 7 on page 6 of this
Instruction Manual

 

   QUARTZ TUBE INSTALLATION

Install heater so that the quartz tubes are
horizontal. Failure to do this may cause the
heating element within the tube to sag and cause
premature burnout. 

 

 
 
 

 

 
 
 

 

ELECTRICAL SHOCK 
HAZARD 

 

• 

Serious injury or death 
may occur. 

 

• 

Disconnect from electrical 
supply before installing or 
servicing this heater. 

 
 
 

   HEATER INSTALLATION

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

These heaters MUST be installed as follows: 
 

 

12 inches minimum from a vertical surface 

 

 

24 inches minimum from ANY combustible 
material 

 

 

3 inches minimum from the ceiling 

 

 

36 inches minimum from other heaters 

 

MINIMUM INSTALLATION CLEARANCES 

 
FIRE HAZARD 

 

• 

Serious injury or death 
may occur. 

 

• 

Read and follow 
clearances shown in box at 
left for ALL OCH series 
heater installations. 

 
 
 

 
 

 
 
 
 

NOTE: For optimum spot heating performance, it is recommended that the distance from the floor 
should be approximately 7 to 9 feet for OCH-46 models, and 8 to 10 feet for OCH-57 models. 

Issue Date: 7-21-03       Rev. Date: 9-15-03       Rev. Level: 03       ECN: GP-5005       OIPM P/N: 3420367       

Page 3 of 7

 

 

Содержание OCH–46-120V

Страница 1: ...N GP 5005 OIPM P N 3420367 Page 1 of 7 IMPORTANT SAFETY INFORMATION INSIDE Serious injury or death possible Read understand and follow all safety information and instructions in this manual before using or servicing this product Retain these instructions for future reference CONTENTS Specifications Page 2 Tube Installation Page 3 Heater Installation Page 3 4 Wiring Page 5 Replacement Parts Page 6 ...

Страница 2: ...ion box adds 2 384 to Dim A Model P N Tube P N Watts Volts Amps Cordset Dim A Dim B Dim C OCH 46 120V 04804402 04432302 1500 120 12 5 YES 42 0 5 375 6 500 OCH 46 208V 04804502 04418102 2000 208 9 6 42 0 5 375 6 500 OCH 46 240V 04804602 04418002 2000 240 8 3 YES 42 0 5 375 6 500 OCH 46 277V 04804702 04419302 2000 277 7 2 NO 42 0 5 375 6 500 OCH 46 120V SS 04805202 04432302 1500 120 12 5 YES 42 0 5 ...

Страница 3: ...tubes are horizontal Failure to do this may cause the heating element within the tube to sag and cause premature burnout ELECTRICAL SHOCK HAZARD Serious injury or death may occur Disconnect from electrical supply before installing or servicing this heater HEATER INSTALLATION These heaters MUST be installed as follows 12 inches minimum from a vertical surface 24 inches minimum from ANY combustible ...

Страница 4: ...is shipped complete with hardware for overhead suspension in two different ways 1 In the hardware bag shipped with your heater you will find two adjustable mounting brackets and fastening screws that should be assembled as shown in figure 1 Once assembled to the heater and mounted these brackets enable the heater to be angled in 15 degree increments up to 45 degrees The mounting centers for the br...

Страница 5: ...upply Hi temp wires INTERNAL WIRING DIAGRAM OCH heaters are equipped with two 12 gauge hi temperature silicone lead wires and a ground termination For field wiring use 12 ga 90º C rated wire and connect to the two lead wires in the junction box with wire nuts Make sure ground wire is properly connected to the fixture s ground terminal located in the junction box Make certain the power source confo...

Страница 6: ...RIPTION 1 1 SEE HOUSING TABLE HOUSING 2 1 8561700 COVER JUNCTION BOX 3 1 8561400 8560300 WIRE CHANNEL OCH 46 series WIRE CHANNEL OCH 57 series 4 1 3104600 JUNCTION BOX 5 1 SEE CORDSET TABLE CORDSET STRAIN RELIEF not shown 6 2 8561200 END CAP 7 10 2326500 SCR HWHS 8 32 x 3 8 8 1 8521500 NIPPLE CHASE not shown 9 1 8500739 SPACER not shown 10 1 8561800 8560400 REFLECTOR OCH 46 series REFLECTOR OCH 57...

Страница 7: ...ocation as the company may designate This warranty does not obligate Fostoria Industries Inc to bear the cost of labor in replacing any assembly unit or component part thereof nor does the company assume any liability for secondary charges expenses for installing or removal or any other consequential losses The company s maximum liability shall not in any case exceed the list price for the product...

Отзывы: