DISABLED REFUGE EVC
PAGE 17
3-ZONE REFUGE EVC SYSTEM MANUAL V1.00
File:DR 7700-000 SM7 V100 Refuge EVC Manual 3-Zone.Docx E+EO (c) 2018 Folknoll Group Ltd
PAGE 17
8.2.3
Controller / PSU / Cables
Any control equipment and exposed cable routes should undergo regular visual inspections to check:
•
All control equipment and exposed cable routes show no signs of physical damage e.g. water
ingress, impact
•
All control equipment and exposed cable routes show no signs of other forms of abuse
•
All control equipment and exposed cable routes show no signs of any other forms of damage
that might affect operation
8.3
FUNCTIONAL TESTING
The system should undergo frequent functional testing to ensure that the system is ready for
emergency operation.
8.3.1
User Call Check
For each outstation check the following:
•
A call to the master station can be initiated by the outstation user
•
The master station responds correctly and the master station operator can accept the call
•
The outstation user can be clearly heard by the master station operator
•
The master station operator can be clearly heard by the outstation user
•
The call can be cancelled by the master station operator
8.3.2
Operator Call Check
For each outstation check the following:
•
A call to the outstation can be initiated by the master station user
•
The outstation user can be clearly heard by the master station operator
•
The master station operator can be clearly heard by the outstation user
•
The call can be cancelled by the master station operator
8.3.3
All Call Check
For each outstation check the following:
•
An all call can be initiated by the master station user
•
The master station operator can be clearly heard by the outstation user
•
The all call can be cancelled by the master station operator
8.3.4
Standby Operation Test
Disconnect the mains supply and check the following:
•
The master station reports power fail
•
The sounder can be silenced by pressing the master station
MUTE
button
•
The system is still operational (check that calls can be made)
Restore the mains supply and check the following:
•
The master station no longer reports mains fail