Flexco H-Type Скачать руководство пользователя страница 7

5

 

In certain applications it is necessary to modify the location of the precleaner pole due to permanent obstacles that 

obstruct the desired location. Relocating the pole location can be done easily and does not hinder the performance of the 

cleaner as long as the “C” dimension is maintained. 

 

NOTE: 

In the following example we will be lowering the pole location in the “Y” direction, but the same method  

 

 

could also be applied in the “X” direction. 

  Conveyor 

situation:

 

 

Pulley Diameter: 900mm 

 

 

X = 322mm

 

 

Y = 482mm

 

 

C = 580mm

1.  Determine the given location dimensions and define the change needed.

 After laying out the given X & Y 

dimensions, determine the distance of the modification required for adequate clearance of the pole and tensioning 

system. (In the example we decide to lower the pole 50mm to clear the support structure). 

2.  Write down known dimensions. 

We can now determine two of the three required dimensions which will allow us to 

find the third. We know we cannot alter the “C” dimension, so this will remain the same. Also we are required to lower 

the unit in the “Y” dimension 50mm, so we add 50mm to the given “Y” dimension.

 

X = ?"

 

Y = 482mm + 50mm = 532mm

 

C = 580mm

3.  Determine final dimension. 

On a flat vertical surface, using a level, draw one horizontal line and one vertical line 

creating a right triangle (Fig 3a). Measure down from the intersection the determined “Y” dimension and mark (Fig 

3b). With the tape measure starting at the modified “Y” mark, swing the tape across the “X” line and mark at the “C” 

dimension where it crosses the “X” line (Fig 3c). Measure from the intersection to the “C” intersection and this will be 

your new “X” dimension (Fig. 3d).

 

X = 231mm

 

Y = 532mm

 

C = 580mm

 

 

 

 

Fig. 3a

Fig. 3b

Fig. 3c

Fig. 3d

mark

This distance is 

new “X” dimension

C (580mm)

Y (532mm)

900mm

X

C

Y

(231mm)

3.2  Cleaner Location Adjustments

Section 3 - Pre-Installation Checks and Options (cont.)

Содержание H-Type

Страница 1: ...H Type Precleaner with XF2 Tips Installation Operation and Maintenance Manual www flexco com www flexco com...

Страница 2: ...chased From _____________________________________________________________ Installation Date _____________________________________________________________ Serial number information can be found on the...

Страница 3: ...ation Instructions 6 4 2 Pole Location Charts 9 Section 5 Pre Operation Checklist and Testing 10 5 1 Pre Op Checklist 10 5 2 Test Run the Conveyor 10 Section 6 Maintenance 11 6 1 New Installation Insp...

Страница 4: ...ice 91 44 6551 7771 Visit www flexco com for other Flexco locations and products Please read this manual thoroughly and pass it on to any others who will be directly responsible for installation opera...

Страница 5: ...isengage any takeups Clear the conveyor belt or clamp securely in place Use Personal Protective Equipment PPE Safety eyewear Hardhats Safety footwear Close quarters springs and heavy components create...

Страница 6: ...rts are included Review the Tools Needed list on the top of the installation instructions Check the conveyor site Will the cleaner be installed on a chute Is the install on an open head pulley requiri...

Страница 7: ...itedownknowndimensions Wecannowdeterminetwoofthethreerequireddimensionswhichwillallowusto findthethird Weknowwecannotalterthe C dimension sothiswillremainthesame Alsowearerequiredtolower theunitinthe...

Страница 8: ...B Belt Direction Fig 2 Physically lock out and tag the conveyor at the power source before you begin cleaner installation Pole Location Specs For specific cleaner specs see charts on page 8 A X C A P...

Страница 9: ...tion marks Intersecting mark Y X Fig 5 11 Position the pole Rotate the pole upward until the tips touch the belt Center the tips across the belt While applying light pressure on the center tip shift t...

Страница 10: ...r tensioning Make adjustments as necessary 14 Reassemble the spring assembly Slide the spring washer and bushings onto the pivot arm and turn the two adjusting nuts so about 6mm 1 4 of the pivot arm i...

Страница 11: ...2 527 29 850 314 435 537 29 875 327 438 546 25 900 340 441 559 25 925 352 445 568 25 Medium M XF2Tips for Head Pulley Diameters 650 to 1125mm Diameter Over Belt X Y C Gap 650 206 451 495 64 675 219 45...

Страница 12: ...d from the belt and the conveyor area 5 2 Test Run the Conveyor Run the conveyor for at least 15 minutes and inspect the cleaning performance Check the tensioner spring for recommended length proper t...

Страница 13: ...that are dirty If the blade is worn out and needs to be replaced If there is damage to the blade or other cleaner components If fugitive material is built up on the cleaner or in the transfer area If...

Страница 14: ...y are flush with the ends of the pivot arms Fig 1 This releases the tension of the blade on the belt Physically lock out and tag the conveyor at the power source before you begin cleaner installation...

Страница 15: ...oper tensioning Make adjustments as necessary 3 Install the new tips Locate each tip onto each suspension arm then install the hardware to fasten the tip to the cushion Fig 3 HXF2 Spring Length Chart...

Страница 16: ...ty Date Work done by Service Quote Activity Date Work done by Service Quote Activity Date Work done by Service Quote Activity Date Work done by Service Quote Activity Date Work done by Service Quote A...

Страница 17: ...cted Is blade making complete contact with belt Yes No Blade wear LEFT MIDDLE RIGHT Blade condition Good Grooved Smiled Damaged Measurement of spring Required Currently Was Cleaner Adjusted Yes No Pol...

Страница 18: ...sual wear or damage to blade Mechanical splice damaging blade Repair skive or replace splice Belt damaged or ripped Repair or replace belt Cleaner not correctly located Verify C dimension relocate to...

Страница 19: ...For special extra long pole length requirements a Pole Extender Kit 76024 is available that provides 750mm 30 of extended pole length Pole Diameter 73mm 2 7 8 HXF2 Spring Length Chart for optimal bla...

Страница 20: ...3 1 8 13 1 2 13 3 8 13 1 4 12 5 8 12 3 4 12 1 2 12 7 8 DIAMETER OVER BELT 2 1 2 2 7 8 3 3 8 3 7 8 POLE LOCATION CHART 2 10 12 14 13 11 X 11 7 8 12 12 1 8 12 1 4 12 3 8 12 13 Y 1 1 8 1 1 8 1 3 8 1 1 8...

Страница 21: ...8 20 16 1 4 16 3 8 16 1 2 16 1 8 16 18 5 8 19 1 4 19 18 1 4 17 7 8 OVER BELT DIAMETER 16 17 14 15 20 18 19 22 23 24 21 14 5 8 2 3 4 14 7 8 5 1 8 6 5 8 7 1 8 7 5 8 5 5 8 6 1 8 3 3 4 4 5 8 4 1 4 3 1 4 1...

Страница 22: ...3 3 4 24 1 4 25 3 8 25 3 4 24 5 8 26 5 8 26 1 4 18 1 2 11 32 20 16 3 8 17 1 4 16 7 8 44 45 20 1 4 20 1 8 11 1 2 12 1 2 13 1 2 14 3 8 13 7 8 15 3 8 15 7 8 14 7 8 38 41 42 43 39 40 35 36 37 33 34 13 12...

Страница 23: ...LOCATION CHART 21 15 1 8 41 22 1 4 20 1 2 53 52 21 22 5 8 22 3 8 15 5 8 16 1 8 17 1 8 17 5 8 18 1 8 19 1 2 18 5 8 16 5 8 46 49 50 51 48 47 19 20 44 45 43 42 21 5 8 21 3 4 21 7 8 22 1 8 22 30 21 1 8 21...

Страница 24: ...Arms HFC2 75901 4 0 2d H2 F Tip Cushion Neoprene oil resistant for SS HXF2 Tips or SS Susp Arms HFC2SS 77043 4 0 3 HXF2 Tip Extra Small HXF2 SS 75979 3 0 HXF2 Tip Small HXF2 S 75980 3 4 HXF2 Tip Medi...

Страница 25: ......

Страница 26: ......

Страница 27: ...he belt Slide Out Service gives direct access to all impact bars for change out Impact bar supports for longer bar life 4 models to custom fit to the application A belt cleaner for the tail pulley Exc...

Страница 28: ...dwide through superior service and innovation New Door No 51 Anna Salai Nagalkeni Pammal Village Chennai 600 044 Tamil Nadu India Tel 91 44 4856 6762 E mail info india flexco com Visit www flexco com...

Отзывы: