 Step 5: Connect and test electrical supply

 

 

 

All electrical connections must meet the requirements of AS/NZS 3000 standards and be installed 
and certified by a suitably qualified person. 

 

  The appliance is supplied with 1000mm of 3-core cable to a 3 pin plug that will plug into the electrical wall 

socket (electrical wall socket not supplied). 
 

  The appliance can also be hard-wired into the building if required. 

 

  In order to access the electricals, it is necessary to first remove the front cover. 

 

  Follow the ‘

Front Cover Removal P

rocess’ 

in this guide. 

 

  With the front cover removed the electrical connections in the appliance can be seen. 

 

  Following these connection details, using the 3-core cable from the appliance, remove the 3-pin plug and 

hard wire the cable into the building. 

 

 

IMPORTANT: Before testing, ensure the gas valve is turned off. 

 
 
 
 
 

 

 
 
• 

GD13 models have a glass failure safety switch at the base of the 
opening. The safety switch turns the appliance off if the glass is not in 
position. The 3mm pin will need to be held down to complete electrical 
testing. It is recommended that masking tape is used to hold the safety 
pin down.  

 

  NOTE

: The masking tape must be removed once testing is completed.   

 
 
 
 

 

 

Test electrical functions by switching the bottom High/Low switch to LOW, then switch the appliance ON 
using the top On/Off switch. 

 

• 

The fan will start and after approximately five seconds, the pilot will spark. Because the gas supply is turned 
off, the pilot will spark for approximately five seconds then automatically switch off. The fan will continue to 
operate. 

 

• 

NOTE:

 GD13 models have a fan which operates in both LOW and HIGH settings. 

 

• 

Switch to HIGH setting. Ensure that a red light appears on the electrical connections block and the fan is 
operating. 

 

• 

Switch the appliance off. Electrical testing is complete.         

 

• 

Fit the front cover by following the 

‘Front Cover Installation Process’

 in this guide.  

 
 
 

Safety switch pin

 

 

Содержание GD13

Страница 1: ...GD13 Installation Guide Operating Instructions Warranty...

Страница 2: ...ppliance particularly the steel surrounding glass panels to the face or the door become extremely hot during operation and can result in serious injury and burns if touched It is therefore recommended...

Страница 3: ...cific gas bayonet location requirements The appliance is supplied with a 1000mm long electrical cable and 3 pin plug that will plug into the electrical wall socket electrical wall socket not supplied...

Страница 4: ...oing the 4mm Allen head cap screws Gently pull at the top corners in a forward motion The glass will tilt forward In one movement gently pull the glass up and away from the fire to break the magnetic...

Страница 5: ...op sides of the glass and powerful magnets in each lower corner On the back corners of the glass there are 3mm steel magnet panels In one Movement gently lower the glass down allowing the steel magnet...

Страница 6: ...25mm clearance from combustible materials 75mm clearance from wiring and plastic pipes and a minimum of 5mm from non combustible materials is required when installing a flue system for any appliance s...

Страница 7: ...ntroller the cover panel will need to be lowered carefully and remain close to its original position Front Cover Installation Process Fit the front cover which is held in place by 9 x 5mm cap screw 3...

Страница 8: ...dels have a glass failure safety switch at the base of the opening The safety switch turns the appliance off if the glass is not in position The 3mm pin will need to be held down to complete electrica...

Страница 9: ...Version June 2019 9...

Страница 10: ...afety pin down NOTE The masking tape must be removed once testing is completed Switch the appliance on Test adjust high first and then the low pressures against rating plate specifications The GD13 ha...

Страница 11: ...ould be taken when placing the firebed mediums into the burner tray Failure to place the medium correctly may result in the fire performing inefficiently Open the firebed cardboard box and identify fi...

Страница 12: ...empty the bags of vermiculite into the burner tray Ensure not to spill any vermiculite in cavities in front of and behind burner tray Do not pour vermiculite directly into burner slots Fill area behin...

Страница 13: ...e appliance off and slightly repositioning rocks and logs at the problem areas Repeat this switching on off and repositioning until a natural and non uniform flame effect is achieved Once a natural an...

Страница 14: ...erate appliance Following the GD13 Operating Instructions on the next page show the owner how to switch the appliance on and off and how to switch between high and low settings If the owner is not ava...

Страница 15: ...on off switch to the ON position Press the high low switch to the HIGH position The electronic solenoid pack will start to click Gas will then be released and ignited at the pilot valve The safety sen...

Страница 16: ...oor pilot flame 3 Signal to flame rectifier interrupted 1 Check gas supply 2 Check flame size and pilot flame pressure 3 Check flame rectifier and wire to sit pack Flame in not running the full length...

Страница 17: ...warping if a firebox outer skin or support frame defect occurs contact The Fire Dept and the defect will be repaired or replaced at our discretion with all costs covered The Fire Dept warrants the SI...

Отзывы: