Quadnet Control Panel Engineering and Commissioning Manual
64
Installation Checklist
Use the following checklist to ensure that your work is correct and that the commissioning engineer has the
necessary information to complete the commissioning of the system
The commissioning engineer will require this sheet, along with ‘Loop Continuity and Insulation Test
Results’, correctly marked ‘as-wired’ drawings and completed ‘Configuration sheets’, before attending site
to commission the system.
Stage 1
Description
Loop Checked by
Installation Engineer
Loop Checked by
Commissioning
Engineer
1
2
3
4
1
2
3
4
Loop cable installed correctly, clipped or in
containment.
All loop bases and back boxes installed and
terminated.
All devices have positive core links in place.
Loop insulation and continuity testing complete, and
form filled out.
As-wired drawing marked up showing cable runs
and devices.
Configuration sheets completed with devices
descriptions etc.
Control Panel backbox installed with 230V AC
supply live, tested and isolated locally
Stage 2
Depending on the terms of your contract, you may also be required to carry out ‘Stage 2’.
Description
Loop Checked by
Installation Engineer
Loop Checked by
Commissioning
Engineer
1
2
3
4
1
2
3
4
Devices installed into bases and backboxes
Detector dust covers fitted
Serial numbers noted on drawings and
‘Configuration Sheets’
Site Name & Address:
Installation Company:
Testing Engineer:
Signature:
Date: