10
INSTALLATION
WALL UNIT INSTALLATIONS
AIR VENT
CONDENSATE DRAIN
Fig . 1
Fig . 3
Fig . 4
INGRESSO ACQUA
USCITA ACQUA
ISOLAMENTO
NO
INGRESSO ACQUA
USCITA ACQUA
ISOLAMENTO
SÌ
INGRESSO ACQUA
USCITA ACQUA
NO
1 .
The insulation must cover both water inlet and outlet pipes as shown
2 .
Use polyethylene insulation (minimum thickness 8mm) .
1 .
Connect the water inlet and outlet pipes, turn the unit on and set it
to cool mode; make sure the valve opens .
In this way water starts entering the coil .
2 .
Check for water leaks along the hydraulic connections .
If there are no leaks, open the air vent and air starts coming out of
the coil .
Attention: During these operations, be careful not to touch live
electrical parts .
3 .
Close the air vent .
Carry out the condensate drain pipe connection, making sure nothing
can hinder the natural drainage of the condensate which forms in
cooling mode .
Proceed as follows:
Ensure a minimum slope for the flow of condensate
Avoid any hindrances to the flow
After connecting, make sure the water flows properly out of the
machine .
1 . Connect the condensate drain pipe .
2 . Make sure the drain pipe does not have traps or curves that hinder
the flow of condensate .
3 . Check correct flow by pouring water into the tray and make sure it
comes out through the drain pipe installed .
Fig . 2
WATER INLET
WATER INLET
WATER INLET
WATER OUTLET
INSULATION
INSULATION
WATER OUTLET
WATER OUTLET