background image

3

  

0800 002 725

  

|

  

fentec.co.nz

STEP 1 - 

MARKING OUT POST HOLES

STEP 2 - 

INSTALLING POSTS

A STEP-BY-STEP GUIDE 

TO INSTALLATION

Soil Type

Minimum Hole Depth

Approximate Concrete Required

Clay / Firm Earth

600mm

2 bags per hole (20Kg bag)

Sand / Loose Fill

900mm

3 bags per hole (20Kg bag)

If it isn’t possible to fix posts as 
proposed here, please contact us for 
further information. 

Start post may 

be existing or 

temporary peg

Dig holes 

according to 

depth chart 

below

All holes should be straight 

(i.e. Sides parallel or wider 

at the bottom than the top

Diameter of all holes is 

250mm minimum.

Marker pegs

Mark out post c

entr

es

IMPOR

TANT

IMPOR

TANT

2 .1

2 .2

Fastening posts together

Fixing posts in ground

Approx. 

40mm

2 Fasteners approx. 

60mm from top of 

post 

Maximum screw spacing 

300mm centres

10 - 16 x 16mm 

self-drilling screw 

placings.
Screws to conform to 

AS3566 Class 3.

-

 Place first post in hole

-

 Adjust to correct height

-

 Support post with temporary brace

-

 Fill hole with fully mixed, wet concrete

Vibrate and compact the concrete to remove voids.

Align vertically with 

spirit level in both 

directions 

Do not allow soil, 

garden fill and/or dirt 

to come in contact with 

posts as this may cause 

the post to corrode

Slop top of 

concrete away 

from post (to drain 

away water)

Bottom 

rail approx. 

50mm 

above 

ground

Nominal  

30mm

1800mm = 1830mm

Отзывы: