END PANEL INSTALLATION (continued)
15. Standing outside the door, install Tek screws through
door frame and into end wall frame member to secure.
Tek screw
14. Cut panel(s) to proper height after attaching to end wall
frame.
Cut upper panel
to proper length.
ATTENTION:
In above photo, top of panel is removed
using a power tool equipped with a round cutting bit.
Greenhouse in photo used for illustration only. It is of a
different model.
Review roof panel installation steps later in this guide
to determine end panel position and length. Panel
to remain flush with top of end rafter pipe. See also
how panels are sealed after roof panel installation is
complete.
16. Repeat procedures (as needed) to install remaining
end panels for other end of greenhouse.
NOTE:
Consult Quick Start section for additional
information.
17. Continue with
Main Cover Installation
procedures on
the next pages.