Install Gutters
Complete these steps:
1. Using the diagram on the previous page, pick the gutter section
and set it in place on the pod frame.
2. Ensure that the gutter slopes toward the downspout location
shown on the diagram.
ATTENTION:
Downspout is installed
after
all gutters are
installed.
3. Set all trays in place on the frame where gutter was installed.
4. Mark two (2) locations between trays at each end of the gutter.
ATTENTION:
For the shorter, 2-tray gutters, install one (1)
screw between the two trays. For all other gutters, position all
fasteners between the two trays at each end regardless of how
many trays are on each pod level.
5. Remove the trays and drive a 112838 Tek screw through the
gutter and into the frame tube at the locations chosen in Step 4.
6. Repeat this procedure to install all remaining gutters.
7. Continue with the installation of the downspouts.
INSTALL GUTTERS—continued
STEP 5
STEP 4
STEP 6
STEP 3
Set trays on frame to judge where to install
fasteners to secure gutter to frame.
Slide trays back from gutter to allow for the
installation of the 112838 fasteners.
Center fastener location so screw head does
not contact any part of any tray.
Photo shows trays in position with fastener
installed to secure gutter.
Screw Locaton
Photo shows installed gutter. Dashed arrow
indicates direction of water flow.
STEP 2
Gutter end
is tight to
frame tube.
STEP 1
Photo shows crimped or high end of gutter,
which is opposite the drain end.