Operation - 2895 Loader
Installing Loader:
1. Position the tractor centrally and parallel to
the loader uprights. Drive forward slowly until
the loader hydraulic hoses can be coupled.
Shut tractor off and set park brake. Couple
the loader hoses to the matched color code
identifiers on the auxiliary valve for proper
orientation of loader operation.
2. Extend lift cylinders to tilt both loader uprights
approximately 30 degrees. Rollback bucket to
further raise upright for additional clearance.
Both upright base pivots must be above the
loader mount cradle.
CAUTION
Prior to initial mounting, cycle loader cylinders to displace air. This
ensures the loader will remain in the storage position and operate
consistently.
CAUTION
Verify front and side clearances during installation to position
hydraulic hoses such that they will not be pinched or stretched
during installation.
3. Slowly drive the tractor forward until the
upright base pivot contacts the mount
plate.
4. Slowly extend the bucket and retract the lift
cylinders to lower the upright pivot into the
mount plate cradle. Ensure both uprights
are fully engaged within the mount plate
cradle.
Содержание Allied 2895
Страница 1: ...Operator and Parts Manual 122011 P4110 2895 Loader For serial numbers 0528950045 and later ...
Страница 2: ......
Страница 6: ...6 Specifications 2895 Loader Specifications ...
Страница 31: ......
Страница 36: ...36 Parts 2895 Loader Main Frame Assembly ...
Страница 38: ...38 Parts 2895 Loader Hydraulic Plumbing Assembly ...
Страница 40: ...40 Parts 2895 Loader Main Frame Assembly TSL ...
Страница 42: ...42 Parts 2895 Loader Hydraulic Plumbing Assembly TSL ...
Страница 49: ......