Programming time of enclose
1. Press and hold a button PROG for time when green LED U start to
pulsate.
2. When we again press a button PROG (START). Controller start
count a time which is to signal by pulsate of green LED.
3. Press again a button PROG (STOP). Controller remember a
counted time. Programmin mode is automaticly closed ( green LED U
shine continually).
* If at time 30 sec from activate programming mode a
count of time doesn’t to start, then controller will out from
programming mode.
* Max time for programming 10min. Test by long time than
10 min to cause controller automaticly out from
programming mode.
* Input to programming mode posible is only when motor
of roller is OFF.
* In programming mode a controller doesn’t to react for
outward control signal .
Do not install to device which is broken or incomplete.
During assembly of controller should be take special care
Wrong connection could cause to give a shock and/or
break controller or connected device.
5. Controlled roller motor connect properly to joints 10 and 12 and to N.
To joint 11 connect to supply (L) of motor.
6. Take ON the power.
7. Programm time of upwards/downwards of roller. Prescribed is that
programmed time should be longer than 10 sec from real time of
upwards/downwards.
4. Choose control option (control impulse L or N). Switch of local
control and central control connect with marks with function to joint to
choosen cable (accordance with choosen control option - L or N).
3. Connect power cable to joint 1-3 with marks.
Group of controllers which working with common central
control should be supplied from the same phase e.g only
L1.
All control inputs of controllers which works separately or
in group should have to common control impulse option -
all are controlling from the same phase, e.g. only L1 or all
from N.
Connection different phase e.g. L1 and L2; or phase L
and “zero" N to inputs of control inputs of controller can
cause to wrong work of system and break controllers.
Choosing control option from phase (L) to control inputs
should be connect to the same phase as for supply e.g.
only phase L1.
ASSEMBLY
1. Take OFF the power.
2. Put on the controller on the rail in the switchgear box.
supply
230V AC
current load AC-3
<2A
control pulse current for L/N
<1mA
power supply indicator
LED green
power supply indicator
working temperature
-25÷50°C
connection
screw terminals 2
dimensions
1 module (18mm)
2×LED red
power consumption
0,8W
,5mm²
fixing
on rail TH-35
TECHNICAL DATA
A090619