Programming time of enclose

1. Press and hold a button PROG for time when green LED  U  start to 
pulsate.
2. When we again press a button   PROG (START). Controller start 
count a time which is to signal by pulsate of green LED.
3.  Press  again  a  button    PROG  (STOP).  Controller  remember    a 
counted time. Programmin mode is automaticly closed ( green LED U 
shine continually).

*  If  at  time  30  sec  from  activate  programming  mode  a 
count of time doesn’t to start, then controller will out from 
programming mode.
* Max time for programming 10min. Test by long time than 
10  min  to  cause  controller  automaticly  out  from 
programming mode.
* Input to programming mode posible is only when motor 
of roller is  OFF.
* In programming mode a controller doesn’t to react for 
outward control signal .

Do not install to device  which is  broken or incomplete.

During assembly of controller should be take special care 
Wrong  connection  could  cause  to  give  a  shock  and/or 
break controller or connected  device.

5. Controlled roller motor connect properly to joints 10 and 12  and to N.
To joint 11 connect to supply  (L) of motor.
6. Take ON the power.
7. Programm time of upwards/downwards of roller. Prescribed is that 
programmed  time  should  be  longer  than  10  sec  from  real  time  of   
upwards/downwards.

4.  Choose  control  option    (control  impulse  L  or  N).  Switch  of  local 
control and central control connect with marks with function  to joint to  
choosen cable (accordance with choosen control option - L or N). 

3. Connect  power cable to joint  1-3  with marks.

Group of controllers which working with common central 
control should be supplied from the same phase e.g only 
L1.

All control inputs of controllers which  works separately or 
in group should have to common control impulse option -  
all are controlling from the same phase, e.g. only L1 or all 
from N. 

Connection different phase e.g. L1 and L2; or phase L 
and “zero" N to inputs of control inputs of controller can 
cause to wrong work of  system and break controllers.

Choosing control option  from phase (L) to control inputs 
should be connect to the same phase as for supply  e.g. 
only phase  L1. 

ASSEMBLY

1. Take OFF the power.
2. Put on the controller on the rail in the switchgear box.

supply

230V AC

current load AC-3

<2A

control pulse current for L/N

<1mA

power supply indicator

LED green

power supply indicator

working temperature

-25÷50°C

connection

screw terminals 2

dimensions

1 module (18mm) 

2×LED red

power consumption

0,8W

,5mm²

fixing

on rail TH-35

TECHNICAL DATA