- 7 -
1. Disconnect the power supply.
2. The indicator mounted on a rail in the distribution box.
3. Connect the power in accordance with the markings to the
terminals 18 (L1), 17 (L2), 16 (L3).
4. N-wire connect to terminal 15.
5. Transformers fasten on the phase conductors and secondary
outputs connected in accordance with the indications to the
terminals: 1-2 (L1), 3-4 (L2), 5-6 (L3).
If the secondary circuit of the transformer is opened
during operation, there is a risk of high voltage on the
secondary winding. In order to protect personnel opera-
ting the device, it is recommended to ground one end of
the secondary winding of each transformer.
Do not tighten the terminals without an inserted wire.
This may damage the clamping mechanism or the plastic
cover of the terminal.
6. Connect the RS-485 network cables to the terminals 10 (B)
- 11 (A).
7. Additional pulse receiver connected to terminals 9 (+) - 8 (–).
Additional pulse receiver is not required.
8. Put the meter terminals covers.
9. If required, the casings should be sealed.