Installation Instructions

ALL INSTALLATION WORKS TO BE CARRIED OUT BY COMPETENT PERSONNEL - INSTALL AS COMPLETE UNIT

Tord Lounger

1.  Install suitable foundation pads (see illustration) each with top face at ground level.
2. Attach base assembly to upper frame using the 4 no. M10 x 25mm csk bolts and locknuts - tighten to 14Nm.
3. Position lounger in correct orientation with base legs centrally on foundation pads; then mark hole positions 
    through base frame.
4. Remove the lounger; drill holes Ø12mm x 125mm deep or as per manufacturer’s recommendations.
5. Clear debris from holes.
6. Fill the holes to within approximately 35mm from the top with Hilti HY150 resin (or similar). Lift the lounger 
    (with threaded anchor rods/capnuts in place) and carefully lower the anchors into the holes, leave for two 
    hours before using.
7. Using a torque wrench, tighten nuts and washers anchoring base to 30Nm to fasten down the lounger.
8. Check level.

IMPORTANT NOTES:

Ensure  that  stainless  steel  is  protected  during  site  cutting  of  stone  –  contamination  from  disc  cutters  will 
produce corrosion on stainless steel components.