manualshive.com logo in svg
background image

T

HE

 455 D C

ONTROL

 P

ANEL

 

G

ENERAL

 D

ESCRIPTION

 

 

The FAAC 455 D control panel is used to operate the 

following models. 

 

 

Swing gate operators

400  

415

 

402  

750 

422  

760 

 

Barrier gate operators: 

 

 

615

 

 

The 455 D programming controls the following: 

 

Operating logic

:  A,  S,  E,  EP,  B,  AP  and  C 

logics available. 

 

Reversing device behavior

: Choose whether a 

triggered reversing device during closing 

immediately reverses gate movement or stops 

the gate and reverses gate movement when no 

longer triggered. 

 

Torque or Pressure

: Force adjustment for the 

415 operator. Adjustable from 0 to 50. 

 

Caution

: For all hydraulic operators, the torque  

must

 be programmed to the maximum (50) 

setting. 

  

Pause time between opening and closing

adjustable from 0 to 240 seconds. 

 

O p e n i n g / C l o s i n g   t i m e

:   a d j u s t a b l e 

 

from 0 to 4 minutes. (Programmable) 

 

Leaf delay on closing

: adjustable from 0 to 4.1 

minutes. 

 

The 455 D control panel should be installed in an 

enclosure that is conveniently located as close as 

possible to the gate operator. All electrical 

connections from the control panel to the operator 

must be made in a weatherproof junction box. 

 

The 455 D control panel requires a single-phase 

power supply voltage (115 VAC [±10%] or 230 VAC 

[+6 or -10%], 50–60 Hz). The power supply should be 

protected by a 15 amp dedicated circuit breaker (not 

provided). 

 

The installer is responsible for grounding the 

operator system, for providing the main power 

breaker switch, and for making sure that the entire 

gate system meets all applicable electrical codes.

 

 

N

OTE

An installation is U.L. compliant only 

when you install the FAAC operators according 

to the UL325 standards. 

 

 

I

NSTALLING

 

THE

 455 D C

ONTROL

 

P

ANEL

 

 

Locate the control panel in the most convenient position 

possible, considering the movement of the gate.   

 

Installing the control panel consists of the following 

general steps: 

 

∗ 

Connecting the main power to the control 
panel  

∗ 

Connecting the activating device 

∗ 

Connecting the operator to the control panel 

∗ 

Checking the direction of the motor's rotation 

∗ 

Connecting other devices to the control panel 

∗ 

Set operating modes 

 

 

C

ONNECT

 

THE

 M

AIN

 P

OWER

 S

UPPLY

 

 

WARNING! 

Turn the main power off before you 

make any electrical connections or before 

programming. 

 

Wire the main power supply to control panel terminals 

in block J3 (see Figures 15 and 16). The installer is 

responsible for insuring that a separate, grounded 

circuit protected by a circuit breaker is between the 

control panel and the main power supply. All wiring 

should conform to applicable electrical codes, and all 

wiring and fittings should be weatherproof and/or 

suitable for burial. 

 

Connect the ground to the grounding terminal in block 

J3 and connect the power wires to the terminals labeled 

N (neutral) and L (line). 

 

N

OTE

:  

For a 230V system, a neutral is not 

needed.  Connect one 115V line to the L (Line) 

and a second 115V line to the N (Neutral).   

Pag e 14 

M a y,   20 06  

4 1 5 L LS Ope ra tor  And  

4 5 5  D  C ontrol   Pa ne l  I nsta ll a ti on  Ma nua l  

T

HE

 455 D C

ONT

R

OL

 P

ANE

L

 I

NSTALLA

T

ION

 I

NS

TRUCTIONS

 

Содержание 415 L LS

Страница 1: ...the Operator 7 Install the 455 D Control Panel 10 Exploded View 415 L LS 12 415 L LS Parts List 13 The 455 D Control Panel General Description 14 Installing the 455 D Control Panel 14 Connect the Mai...

Страница 2: ...affected by the size of the gate how often it is used and how fast the gate operates 2 The operator you choose to install on your gate must be designed for the type and size of your gate and for the...

Страница 3: ...ower before making any attempt to repair it 4 Do not attempt to impede the movement of the gate You may injure yourself as a result 5 This equipment may reach high temperatures during operation theref...

Страница 4: ...per hour 25 Maximum leaf length ft m 15 4 5 Maximum leaf swing deg 110 Thrust and traction ft lb Nm 221 300 Stroke in cm 15 38 1 Rod speed in sec cm sec 3 4 1 85 Operating Ambient Temperature Deg F De...

Страница 5: ...panel 1 415 L LS Operator 1 4 Conductor Electric Cable for Motor Connection 1 3 Conductor Electric Cable for Limit Switch Figure 1 Parts of the 415 L LS Operator Connection 1 Package of mounting hardw...

Страница 6: ...rol Panel see page 19 for Basic Programming Reversing devices such as inductive loops and photocells should be installed to provide non contact reversing operation WARNING To insure that the installat...

Страница 7: ...he installation of the operator Follow the instructions below to install your operator whether in an inward or outward swinging configuration Installing the operator consists of the following steps At...

Страница 8: ...aking sure the dimensions on your gate system match those shown in Figure 9 Outward swinging gate If you are installing the 415 L LS Operator to swing the gate outward construct a steel elbow of suffi...

Страница 9: ...nsions 90 deg Swing 110 deg Swing A 7 5 8 in 195 mm 6 5 8 in 170 mm B 7 5 8 in 195 mm 6 5 8 in 170 mm C 50 3 4 in 1290 mm D Maximum 5 in 125 mm 4 2 5 in 110 mm E Less Than A Less Than A ATTACH THE OPE...

Страница 10: ...is manual Figure 11 Limit Switch Cover with Fastening Screw ADJUSTING THE LIMIT SWITCHES The limit switch adjustments are carried out as follows 1 Unscrew the upper fastening screw figure 11 ref A and...

Страница 11: ...e gate 6 7 8 Operator Wire Gauges for Given Voltage Control Panel Enclosure 115 VAC Photocell A 2 18 AWG A 2 18 AWG Power Switch B 4 14 AWG B 4 14 AWG FAAC 5 Wire Cable for Master Slave Connection and...

Страница 12: ...Page 12 May 2006 415 L LS Operator And 455 D Control Panel Installation Manual The 415 L LS Operator 415 L LS...

Страница 13: ...Switch Protective Cover 1 12 490108 Limit Switch Assembly 1 13 718354 Front Mounting Pin with C Clips 1 14 N A Self Tapping Screws 4 2 mm x 13 mm 7 15 728271 Front Mounting Bracket 1 16 711027 Limit S...

Страница 14: ...g the main power breaker switch and for making sure that the entire gate system meets all applicable electrical codes NOTE An installation is U L compliant only when you install the FAAC operators acc...

Страница 15: ...ire to 2 and the red wire to 3 Wire each leg of the capacitor supplied to terminals 2 3 Note If you want to delay the closing of one gate leaf in a two leaf gate design be sure to connect its operator...

Страница 16: ...leaves should open If a gate leaf closes then you need to turn off the main power and reverse the connection of the red and black wires on terminal block J4 for the operator controlling that leaf Then...

Страница 17: ...he motors without a closed circuit between 11 14 The LED Indicators The nine light emitting diodes LEDs on the control panel can be used to check for the proper function of the devices attached to the...

Страница 18: ...elay is desired it must be enabled in the Advance Programming opening and closing respectively are triggered Use the LEDs and the next table to determine if the accessory devices you have installed ar...

Страница 19: ...vac Relay Lock 12 19 NC C Coil Voltage Motor Voltage Additional Reversing Devices 17 14 9 NO C 14 If 4 Wire Receiver Free Exit Loop Phone Firebox Hold Open Dev ices 14 9 C NO 1 2 1 2 3 4 5 19 17 12 19...

Страница 20: ...am and the display resumes showing the status of the inputs The table on the right shows the sequence of functions accessible in BASIC PROGRAMMING BASIC PROGRAMMING Display Function Default OPERATING...

Страница 21: ...UNCTION If this function is enabled the safety devices operate in compli ance with French standard NFP 25 362 Y Enable No Disabled ADVANCED PROGRAMMING To access ADVANCED PROGRAMMING press the F key a...

Страница 22: ...sired motor run time has been reached an open command must be given to shut the motor off At this point gate operator 2 will automatically start to open When gate operator 2 reaches the position that...

Страница 23: ...r 1 is used you must go through the entire programming procedure as if you were programming a dual gate operating system is being installed 2 When the gate operator 1 has finished opening supply 5 ope...

Страница 24: ...g Reversing Device s Warning Light Closed Opens both leaves and closes them after pause time Opens single leaf connected to Motor 1 and closes it after pause time No effect No effect No effect Off Ope...

Страница 25: ...ning is in hibited No effect opening is inhibited No effect opening is inhibited Off Opening Stops Stops Stops Stops gate closes when reversing device no longer trig gered No effect On Opened Closes b...

Страница 26: ...e system Prevent such inappropriate use by installing separate gates for pedestrians The operating controls for an automatic gate must be secured to prevent the unauthorized use of those controls The...

Страница 27: ...NS BUT DOES NOT CLOSE SOLUTION Make sure you have selected the desired operating mode Verify that the reversing devices are working properly FSWOP and FSWCL should be illuminated except when a reversi...

Страница 28: ...dance with FAAC International Inc s or FAAC S p A s instructions or has been operated under conditions more severe than or otherwise exceeding those set forth in the specifications for such product s...

Отзывы: