4.  System Operation 

Full Chamber Manual Operation 

a)  Ensure main power breaker is ON (Main Power Lamp will be illuminated). 
b)  Turn cooling fans ON (solar array lamps will not function until fans are turned on). 
c)  Turn on solar array by pressing LIGHTING AREA ZONE switches 1-5 sequentially. 

Allow ten (10) minutes for solar lamps to reach full power and spectrum stabilization. 

d)  At completion of test, turn off solar array by pressing LIGHTING AREA ZONE 

switches 1-5 sequentially. 

e)  Turn cooling fan OFF 
f)  Turn OFF Main Power Breaker if desired. 

Programmed Test Operation 

a)  Follow steps a) – c) above. 
b)  Program desired test duration time in hours and minutes on the TEST OPERATION 

HOUR controller. 

c)  Initiate test by pressing TEST START switch 
d)  At completion of test, solar array will automatically shut down, alarm buzzer will 

sound, cooling fans will continue to operate for ten (10) minutes and cooling fan 
switch lamp will flash. 

e)  Cooling fans may be turned OFF by pressing the COOLING FAN switch. 
f)  Turn OFF Main Power Breaker if desired. 

Partial Chamber Operation 

a)  Follow steps a) and b) from Full Chamber Manual Operation section above. 
b)  Turn on solar array segment by pressing the desired LIGHTING AREA ZONE 

switches 1-5 sequentially. Allow ten (10) minutes for solar lamps to reach full power 
and spectrum stabilization. To ensure minimum IEC class C uniformity over entire 
target irradiation area please observe the following guidelines: 

  For QUARTER chamber (650mm x 650mm) target irradiation area, place PV 

panel(s) in chamber at far left (facing chamber) side and turn on LIGHTING 
AREA ZONE switches 1-3 sequentially. 

  For HALF chamber (650mm x 1300mm) target irradiation area, place PV 

panel(s) in chamber starting at far left (facing chamber) side and turn on 
LIGHTING AREA ZONE switches 1-4 sequentially. 

  Refer to Irradiation Intensity Distribution profiles in Section 2 of this manual for 

specific details 

c)  If programmed test is desired, follow steps b) – f) from Programmed Test Operation 

section above. 

d)  If manual test is desired, follow steps d) – f) from Full Chamber Manual Operation 

section above. 

5.  Solar Lamps 

A.  Please allow ten (10) minutes after initial startup for solar lamps to reach full power and 

spectrum stabilization. 

B.  If solar array has been in operation and is shut down (hot re-start), please allow about 20 

minutes to re-start lamps and for solar lamps to reach full power and spectrum 
stabilization. 

C.  For preventative maintenance, the solar lamp life is specified at 3,000 hours of operation. 

Although the lamps will typically last much longer, the lamp life is specified to ensure 
irradiation output and spectrum remain within required IEC class C specifications.   

Содержание Iwasaki Electric ESS0460-H119

Страница 1: ...F08 064 Operating Manual ESS0460 H119 PV Module Solar Soaking Chamber 12 19 2008...

Страница 2: ...tional Iwasaki Electric 9150 Hendricks Road Mentor OH 44060 888 665 2677 support eyeappliedoptics com In order to operate this system properly and prevent potential problems please read the following...

Страница 3: ...r Breaker 3 phase main power switch for system Solar Light Chamber Shields roll down curtains to shield excess light from work area Solar Irradiation Chamber Cooling Air Ducts dual axial blowers direc...

Страница 4: ...nection 3 4 wire RED WHITE BLACK power phase connections and GREEN ground connection single phase solar lamp circuits are equally divided to balance the power over all three phases To protect against...

Страница 5: ...rate meter is assigned to each zone and records the cumulative operation hours for the lamps in that zone Recording the lamp operating time is extremely beneficial for preventative maintenance If less...

Страница 6: ...alarm buzzer will sound Cause of failure could be the lamp inverter starter or wiring defect Solar lamps will shut down but fan will continue for 10 minutes COOLING FAN SWITCH This switch initiates th...

Страница 7: ...ow ten 10 minutes for solar lamps to reach full power and spectrum stabilization To ensure minimum IEC class C uniformity over entire target irradiation area please observe the following guidelines Fo...

Страница 8: ...m irradiation intensity point and allow the calculation of the average irradiation intensity and full target uniformity f If the minimum irradiation intensity is below 850W m2 the irradiation intensit...

Страница 9: ...continuously measured by a type K thermocouple located near the top of the chamber Check the chamber temperature reading at the control panel to ensure an overheat condition does not exist If the temp...