D. 

The allen cap screws should be tightened with the torque wrench to 20 foot-lbs in a 
rotational sequence. The torque wrench will click when the specified torque is 
achieved. This sequence should be repeated two or three times until the twelve screws 
are completely tight. It is imperative that the cap be tightened in a consistent and 
uniform manner to obtain a good seal.  Loosen the top fitting on the cap approximately 
1/8 turn.   

 
E. 

Insert the sample thermocouple through the side of the test cell and tighten the threaded 
gland finger tight and then loosen 1/8 turn. 

 

 
TEMPERATURE CONTROLLER 

 
The temperature controller utilizes a high alarm setpoint which will bring the unit to an alarm 
condition if the temperature ever exceeds this value.  An alarm condition is evidenced by the 
illumination of the "AL1" annunciator in the upper left hand corner of the display.  
 

If the slurry thermocouple is unplugged  
 an alarm condition will occur. 

To adjust the high alarm setpoint perform the following. 
 
1. 

The front cover located on the lower portion of the controller hinges  

downward.   

 
2. 

Depress the scroll key (the right key behind the hinged panel) until a parameter 
appears.  Continue to press the key until the parameter "AL1" appears. 

 
3. 

Press the "UP" or "DOWN" arrow keys until the desired high alarm setpoint is 
obtained.   

 
4. 

Wait approximately 10 seconds and the controller will automatically return to the 
normal display mode.  

 
TIMER 
 

 

The Model 200 incorporates a timer for convenience.  The timer may be activated by 
turning the "TIMER" switch to the "ON" position.  It may be reset to zero at the 
beginning of a test  by depressing the "R" button on the timer's face.  The timer has 
been set in units of hours and minutes but may be programmed to operate in a variety 
of units.  The timer incorporates a relay which can be used to automatically control the 
water cooling solenoid.   

 
 

As an example suppose you wish to ramp the temperature up to 350 F in 1 hour and 
maintain it for four hours.  Setpoint 1 "P1" could be set at 5 hours and set point 2 "P2" 
could be set for 7 hours.  The timer could be reset by depressing the"R" button and the 
"AUTO COOL" switch placed in the "ON" position.  After 5 hours the water solenoid 
would energize and begin cooling the unit.  The unit would cool for 2 hours and then the 
solenoid de-activate. 

Содержание 200

Страница 1: ...essure of the test cell is increased via an air driven hydraulic pump Test temperature is governed by a PID temperature controller which actuates the heater After a predetermined amount of time the temperature of the test cell is reduced by the cooling system Specimens are removed and the compressive strength is determined as outlined in API Specification 10 INSTALLATION 1 Carefully remove the ins...

Страница 2: ...Y MOLDS The slurry shall be placed in the prepared molds in a layer equal to one half of the mold depth and puddled 25 times per specimen with a puddling rod The slurry shall be placed in all the specimen compartments before commencing the puddling operation After puddling the layer the remaining slurry shall be stirred by hand using a puddling rod or spatula to eliminate segregation the molds fil...

Страница 3: ...e controller hinges downward 2 Depress the scroll key the right key behind the hinged panel until a parameter appears Continue to press the key until the parameter AL1 appears 3 Press the UP or DOWN arrow keys until the desired high alarm setpoint is obtained 4 Wait approximately 10 seconds and the controller will automatically return to the normal display mode TIMER The Model 200 incorporates a t...

Страница 4: ...urotherm Model 818 is the most important component of the temperature control system and it is strongly recommended that operators carefully study the Model 818 instruction manual A Program the temperature profile you wish to perform into the Model 818 Controller B Turn the HEAT switch to ON to activate the heaters NOTE THAT THE PRESSURE WILL INCREASE SIGNIFICANTLY DUE TO THE THERMAL EXPANSION OF ...

Страница 5: ...tering the test cell Close all valves and return all switches to the OFF position GENERAL MAINTENANCE 1 One of the most important elements concerning trouble free operation is keeping the interior of the test cell as clean as possible Never insert a cement covered cement mold into the test cell and periodically examine the test cell to ensure that it is clean High pressure valves wear quickly when...

Страница 6: ...For more information please contact us ExpotechUSA 10700 Rockley Road Houston Texas 77099 USA 281 496 0900 voice 281 496 0400 fax E mail sales expotechusa com Website www ExpotechUSA com ...

Отзывы: