Finishing installation
1.
Make sure the circuit breaker / residual current device in the meter
cabinet is in the “On” position and that the main switch in the charging
station is off.
2.
Check the grounding resistance. This should be as low as possible
but not to exceed 150 Ohms. Certain electrical vehicles may need a special
grounding resistance.
3.
Check whether all connectors are tightly connected to the controller
by firmly pressing them into position.
4.
Make sure all switches in the charging station are in the “ON” position
5.
Mount the cover onto the frame by inserting the top into the edge at the top of the
frame and hinging it downwards (figure 9). Be extra careful to align the cover properly to
ensure that the seals are in the right position after the cover closes (IP54 protection).
6.
Check also that the cover locks securely into the open notch at the bottom of the frame
7.
Switch on the supply current at the main distributor / meter cabinet. The charging
station will now carry out a self test. The LED ring around the socket shows the following color
indications during the test (max. 60 seconds)
a)
RED flashing
: Starting up, running test protocol and looking for connection to the
network.
b)
GREEN or OFF:
Stand-by, ready for use.
8.
Check line to line and neutral to line voltages upstream of the power relays, for each
charging point.
9.
Carry out a functional test in accordance with the specifications of the charging station.
For this use a test box for charging
stations
available as an option.
10.
You can now tighten the 4 cover bolts with a Hex key, tightening the nuts evenly and
crosswise. (TIP: use a small ratchet with a Hex key bit – 4 mm)