INSTALLATION INSTRUCTIONS
WALL DRILLING AND BRACKET FIXING
As a first step, proceed with the following drawings:
•
A vertical line up to the ceiling or up to the upper limit, at the center of the area in which the hood is to be fitted.
•
A horizontal line A at 920-1020 mm above the cooker top.
•
A horizontal line B at a X mm above the horizontal line A.
•
A horizontal line C at a 190mm below the horizontal line A.
Mark Points:
•
Mark a point (1) on the horizontal line A, 80 mm to the vertical reference line.
•
Repeat this operation on the other side and on the vertical reference line , checking that the three marks are
levelled.
•
Mark a point (2) on the horizontal line B, 40 mm to the vertical reference line.
•
Repeat this operation on the other side , checking that the two marks are leveled.
•
Mark a point (3) on the horizontal line C, 170 mm to the vertical reference line.
•
Repeat this operation on the other side , checking that the two marks are leveled.
Fix the brackets :
Drill holes at the marked points with a
ɸ
10 mm drill bit.
•
Insert the Wall Plugs 11 into the holes.
•
Fix the hood fixing bracket 20 with 3 screws 10 (5 x 50) at the horizontal line A.
•
Fix a Chimney fixing bracket 21 with 2 screws 10 (5 x 50) at the horizontal line B.
Hook the hood body:
•
Hook the hood body to the bracket 20.
•
Level the hood body itself.
•
Remove the filter from the inside of the hood body, fix the screws 10 to Wall Plugs 11 at the points (3).
Right
Wrong