ETC Installation Guide
Feedthrough Relay Panel Relay Kit
Feedthrough Relay Panel Relay Kit
Page 5 of 5
ETC
6. Install the keyed two pin connector found on the relay wiring harness into the adjacent receptacle on
the relay control board.
7. If the relay wiring harness is not attached to the relay upon receipt, connect the wire leads from the
wiring harness to the low voltage terminals of the relay.
a. Connect the blue wire to the blue screw terminal and secure.
b. Connect the red wire to the red screw terminal and secure.
8. Connect line and load wires to the relay.
a. Strip 6 mm (1/4 in) of insulation from the end of the line and load copper wires.
b. Insert the bare-end into the relay output screw terminals and secure.
Verify Installation
• Are all line and load wires landed into the proper terminal on the correct relay and secured?
• Are all load circuits free of shorts?
• Are voltage barriers used where required by local code?
• Are all cable access openings covered with plugs and all removable plates reinstalled?
• Are all relay low voltage (control) wiring harnesses seated properly in the connector and secured to the
proper low voltage terminals?
• Is the Relay Panel clean of all metal shavings and debris?
• Is the circuit panel schedule updated with the new load information?
Power Up
1. Switch all relays to the OFF position prior to applying power.
2. Re-attach the front cover to the unit.
3. Apply power to the control electronics.
4. At the circuit breaker panel, switch all line feeds to the ON position.
5. Clear any faults that may have caused breakers to trip.
Reference the
Power Control Processor Configuration Manual
for configuration and system test information.
All ETC documentation is available for free download at
.
Loa
d
Lin
e