Operation 

Functionality, fill level

ETAbox Operation

Operation

Functionality, fill level

Pellet transport

The boiler has complete control over the ETAbox. As 
soon as the boiler needs pellets, its control system 
starts the vacuum motor to transport the pellets.
With a time delay (factory setting of 3 seconds for 
an ETA boiler), the boiler control system begins 
to operate the ETAbox's conveyor screw, which 
transports the pellets out of the silo to the suction 
nozzle, where they are sucked out by the vacuum 
motor and transported to the boiler.
To prevent underpressure in the ETAbox, the 
conveying air is returned to the ETAbox through the 
back air hose.
When the boiler has enough pellets, its control 
system switches off the conveyor screw. The 
vacuum pump continues to run (factory setting of 
10 seconds for an ETA boiler) to empty the pellet 
hoses.

Check fill level

The fill level of the ETAbox can be determined 
by feeling the outer wall or visually through the 
inspection ports.

Visual check through inspection ports

Two inspection ports are located at the top of two 
opposing walls. They can be used for a visual check 
of the fill level.

Manual check by feel

Feel along the outside of the bag from top to 
bottom until you feel the pellets.

 Since the pellets take the shape of a funnel as they 

are extracted, the amount of pellets remaining is 
considerably lower than the felt height (see illust-
ration at right).

Back air hose

Suction hose to boiler

Boiler

Suction hose to boiler and back air hose to ETAbox

Inspection port

Remaining 
amount

Resistance

Sheet metal 
base

Fill level

Loose 
fabric

Pellet "funnel"

Felt height

Содержание ETAbox

Страница 1: ...2012 10 22 EN_Englisch User manual ETAbox...

Страница 2: ...of symbols Important NOTICES for operation CAUTION Failure to observe these notices can result in property damage STOP Failure to observe these notices can result in personal injury Warranty guarante...

Страница 3: ...vent damage that neither you nor we wish to occur Training the customer To avoid errors in operation please explain to your customer preferably using this manual exactly how the ETAbox works and how i...

Страница 4: ...plus A1 with a diameter of 6 to 8 mm and a length of 15 to 40 mm If the ETAbox or parts thereof are used for any other purpose no guarantee or functionality claims may be asserted The fabric sack must...

Страница 5: ...the main switch on the boiler before any work on the ETAbox and the pellet conveyor system If the ETAbox has a power supply separate from that of the boiler switch that power supply off as well If th...

Страница 6: ...can be adjusted to the room height in increments of 100 mm ETAbox 17 Length x width 1 700 x 1 700 mm Height adjustable in increments of 100 mm 1 800 to 2 500 mm Volume 3 1 to 5 0 m Weight with pellet...

Страница 7: ...e conveyor screw The vacuum pump continues to run factory setting of 10 seconds for an ETA boiler to empty the pellet hoses Check fill level The fill level of the ETAbox can be determined by feeling t...

Страница 8: ...pen a window to ensure the necessary air flow into the room If the room has no window of its own you can open a door to establish a connection to a room with an open window Use suction During filling...

Страница 9: ...heck fill level regularly Check the fill level regularly to prevent overfilling Do not overfill the ETAbox The current fill level can be determined by looking through the inspection ports or by feel s...

Страница 10: ...lling hose suction hose from the couplings Cover both couplings Switch heating system back on enter pellet level in control system Heating can resume immediately after filling Enter the ETAbox s new p...

Страница 11: ...nozzles on fuel conveying system Pellet hoses leak Conveyor screw transports too many pellets Leak in pellet bin on boiler Non return flap in pellet bin on boiler is dirty ETA boilers have no non retu...

Страница 12: ...the discharge conveyor Use a long pointed object such as a screwdriver to loosen the pellets and remove them Possibly also remove the back air hose to make poking easier Verify whether conveyor screw...

Страница 13: ...the screw disconnect power supply Stop heating and use the mains switch to switch off the boiler If the ETAbox has a separate power supply discon nect it from the mains as well Detach cover on dischar...

Страница 14: ...crews Pull the screw slowly out of the discharge conveyor Removing foreign objects Remove foreign objects from the discharge conveyor or the screw Insert screw into discharge conveyor Slowly insert th...

Страница 15: ...rge conveyor Remove both barrier plates from the discharge conveyor and store them in the immediate vicinity of the ETAbox Attach cover Attach the cover to the discharge conveyor with 2 M8 x 25 hex he...

Страница 16: ...hat you keep records about all service and maintenance work as well as malfunctions These records can be entered in the following pages Then you and our customer service will always have an overview o...

Страница 17: ...17 2012 10 Maintenance and service records ETAbox Operation Date Performed by Service maintenance cleaning Work performed parts replaced...

Страница 18: ...18 www eta co at Maintenance and service records Date Performed by Service maintenance cleaning Work performed parts replaced...

Страница 19: ...19 2012 10 Maintenance and service records ETAbox Operation Date Performed by Service maintenance cleaning Work performed parts replaced...

Страница 20: ...iler is equipped with a draught fan and ventilated rotary valve to protect against back burning Only fill ETAbox at underpressure While injecting pellets extract more air from the ETAbox than is blown...

Отзывы: