19
AFTER INSTALLATION THE END USER SHOULD
KEEP THIS GUIDE FOR FUTURE REFERENCE
DO NOT
THROW AWAY
Post-Installation Checklist
Installation instructions have been understood. Contact
EnviroVent on 01423 810 810 if you require further technical help.
Ductwork diameter is 125mm or larger throughout the property.
The installation system uses rigid duct or a suitable semi-rigid
duct system such as EnviroVent fast track.
Minimal amounts of flexible duct have been used in the
installation.
All ducts, valves, vents and drainage points are connected,
mechanically fixed and sealed.
Both filters are inserted into the filter slots on the unit.
The unit is securely fixed with adequate space left for servicing.
Condensate drain is securely connected to the waste water
system, a non return device is correctly fitted and pipework has
been water tested before connection to the MVHR unit.
All major building works have been completed prior to
commissioning.
Supply and extract air flow rates have been commissioned with
a calibrated anemometer (other suitable devices can be used)
to meet Approved Document F of the Building Regulations for
England and Wales.
Commissioning air flow rate data has been recorded.
The occupants of the property are familiarised with the
operation and maintenance requirements of the system.