Engineered Comfort 35FH Series Скачать руководство пользователя страница 3

Engineered Comfort reserves the right to change any information concerning product or specification without notice or obligation.

Dimensions are in inches (mm).

Page 3 of 4

10/18  EC-35FH-37FH-INST

Ductwork

All ductwork and/or supply and return grilles should be installed 
in accordance with the project plans and specifications. The 
rectangular discharge opening is designed for a flanged duct 
connection. A clear area around the opening has been left for screw 
penetration. Fasten and seal all connections by method prescribed 
in the job specification.

IMPORTANT:

 The dimension from the top of the unit to the top of 

the blower opening changes as the unit is configured for left or right-
hand controls orientation. The unit submittal should be consulted 
to determine appropriate location of unit discharge to facilitate 
ductwork design.
For outside air inlet duct connections slip each inlet duct over 
the inlet collar of the outside air connection. Fasten and seal the 
connection by the method prescribed in the job specification. The 
diameter of the inlet duct in inches must be equal to the nominal 
size of the outside air inlet. The outside air inlet collar is 1/8" (3) 
smaller than the nominal duct size to allow it to fit inside the duct.  

IMPORTANT:

 Do not insert ductwork inside the inlet collar of the 

assembly. For optimum performance, 2 to 3 equivalent diameters 
of straight duct should be installed prior to the outside air inlet of 
the unit. All ducts should be installed in accordance with SMACNA 
guidelines.    

Coils & Valve Package

All valve components should be installed as required, and all 
service valves should be checked for correct operation. If coil and 
valve package connections are to be made by braze or solder, care 
should be taken to assure that no components in the valve package 
are subjected to a high temperature which may damage seals or 
other materials. Valve bodies should be wrapped with a wet rag 
to help dispel heat during brazing or soldering operations. Protect 
adjacent flammable materials when brazing. Use flame and heat 
protection barriers where needed. The chilled water valve package 
should be installed such that all pipes and fittings that extend 
beyond the drain pan are contained in the auxiliary drain pan or 
other device or insulated to prohibit sweating. All piping leading to 
the unit must be sufficiently supported to avoid excessive stress on 
the unit’s piping.  However, adequate free movement is required 
for thermal expansion/contraction. If union connections are used, 
backup wrenches must be used during any tightening process to 
keep the copper tube or fitting from being damaged. Nailor will not 
accept any responsibility for improper tightening procedures that 
damage the connections.
Factory installed threaded connections have been tightened and 
tested at the factory before shipping. These connections must be 
checked for tightness in the field before unit is put into service 
to ensure fittings did not loosen due to shipping vibration. Any 
connection found to be loose must be tightened. Nailor will not be 
held responsible or accept any charges for tightening loose fittings. 
After the connections are completed, the system should then be 
tested for leaks. All water coils must be protected from freezing 
after initial water fill. Even if the system is drained unit coils may still 
retain enough water to cause damage if exposed to temperatures 
below freezing. Shutoff ball valves when ordered as a valve 
package accessory will always ship loose for field install.

Drain Pan

The drain pan is internally sloped toward the drain connection. 

The drain should be checked before initial startup, and periodically 

thereafter to assure that the drain is clear. If the drain is clogged, 

steps should be taken to clear the debris so that condensate will 

flow easily.

Condensate Trap

Install drain line and trap in accordance with all applicable codes. 

A slope of 1/8 in. per 1 ft. of condensate drain line run is necessary 

for adequate condensate drainage. Insulate the drain line to 

prevent sweating. Supports are required for the drain line to prevent 

excessive stress on the drain pan. A drain trap may be required by 

local codes and is recommended for odor control. Each drain pan 

should be individually trapped. See Figure below for details.

Electrical Connections

The unit nameplate lists the unit electrical characteristics such 
as the required voltage, fan and heater amperage, and required 
circuit ampacity. The unit-wiring diagram shows all unit and field 
wiring. Because each project can be different and each unit on a 
project may be different the installer must be familiar with the wiring 
diagram and nameplate on the unit before beginning any wiring. 
An adequately sized fuse, circuit breaker, or disconnect that meets 
local and national electric codes must be supplied. All electrical 
connections should be checked for tightness before startup. All 
field-installed components should be located and checked for 
proper function and compatibility. All internal components should 
be checked for shipping damage and any loose connections should 
be tightened to prevent any problems during startup. Any devices 
furnished by the factory for field installation must be wired in strict 
accordance with the applicable wiring diagrams. Failure to do so 
could result in personnel injury or damage to the equipment and will 
void all manufacturers’ warranties.

H

J

L

P-TRAP

H

 = Maximum negative static  

 

 

pr 1

J

 =  H/2

L

 =  H + J + Pipe di Insulation

Отзывы: