Chapter 3 Installation Testing 11
NetSure 211 C45 Embedded Power Supply System User Manual
Chapter 3 Installation Testing
This chapter introduces procedures of installation testing. The corresponding safety rules shall be adhered to in the
test.
3.1 Installation Check And Startup
Before the test, inform the chief manufacturer representative. Only the trained electrical engineer shall conduct the
system testing. Remove metal objects that may cause shortcircuit, such as rings, watches, and so on.
During operation, watch out for hazardous voltage, and avoid personnel injury and property damage. Before the test,
ground the equipment properly. Installation check must be done before testing, then the batteries can be charged for
the first time.
Make sure that the AC input MCB and load MCBs are switched off. Make sure that all the devices are properly
installed.
Check the system according to the following items listed below.
Installation check
Check item
OK
Comments
Verify all the MCBs, fuses and cables
Verify the system grounding, input and output cable connection
Verify the battery cell number, connection, and battery string polarities
Make sure all the cable connections are firm and reliable
Make sure all the communication cables and alarm cables are connected to the monitoring module. Check
that the temperature sensor, if any, has been installed correctly
Startup preparations
Check item
OK
Comments
Make sure that all the MCB are switched off and all the fuses are removed
Measure the AC input voltage. Make sure the input voltage is within the allowable range
Umin=___V
Check that the battery string circuit is not closed
Connect the disconnected batteries to the battery string circuit
Measure with a voltmeter across the connection points of each battery and make sure that the polarity is
right. For a lead-acid battery with 24 cells, the voltmeter should read 2.0V/cell ~ 2.1V/cell or 48V/battery ~
51V/battery. If the voltage of certain cell is lower than 2.0V, that cell must be replaced
Umin=___V
Check with an ohmmeter that there is no short circuit between the positive & negative distribution busbars,
or between the positive & negative battery poles
(Note: Pull out all modules before the check and restore them after the check)
Startup
Check item
OK
Comments
Switch on the system AC input MCB, and the monitoring module should display the correct voltage and
current values
The green indicator on the rectifier should turn will be on and the fan should will start running. After a
certain delay, the monitoring module should show that the power supply voltage is 53.5V
Check the system voltage and busbar polarity with a voltmeter. The voltage difference between the
measured value and displayed value should be less than ± 0.3V
Start and stop each rectifier by inserting and unplugging the rectifiers. Check their output voltages
Содержание NetSure 211 C45
Страница 6: ......