Section 2: Installation
Installation
2.7 Commissioning
!
WARNING
Installation, commissioning and maintenance and repair works should be made by
qualified staff.
Upon actuator commissioning please carry out the following checks:
•
Check that paint hasn't been damaged during transport, if necessary repair the
damages to paint coat.
•
Check that the pressure and quality of the gas supply (filtering degree, dehydration)
are as prescribed. Check that the feed voltage values of the electric components
(solenoid valve coils, micro-switches, pressure switches, etc.) are compatible with
those reported on the identification plate of the actuator (Figure 1) and to specific
data-plate on electric components.
•
Check that the setting of the components of the actuator control unit (pressure
regulator, pressure switches, flow control valves, etc.) meet the plant requirements.
•
Carry out all kinds of operations and check their proper execution (Section 3.3).
•
Check the absence of leakages in the pneumatic connections.
•
If necessary tighten the nuts of the pipe-fittings.
•
Check proper operation of all the due signalling (valve position, gas supply pressure etc.).
•
Make a complete functional test in order to verify all the operations are executed
according to operating schematic diagram supplied.