Powering the EMC Celerra NS-480 system
For more information, refer to Celerra Tools on http://Powerlink.EMC.com
Power Up procedure for NS-480
Note:
If there are no other components in the cabinet, verify that the cabinet circuit breakers are in
the ON position. If you are installing the NS-480 into an existing cabinet that contains other
components, do not turn off the cabinet circuit breakers. Ensure that the switches on SPS A and
SPS B are in the OFF position.
Connect the power cables as follows:
A yellow circle with a number indicates the power cable number.
1.
Connect power supply A on the fi rst disk-array enclosure (DAE) to
standby power supply (SPS) A .
2.
Connect the power supply B on the DAE to SPS B.
3.
Connect storage processor (SP) A power cable on the SP enclosure to SPS A.
4.
Connect SP B power cable on the SP enclosure to SPS B.
5.
Connect SPS A cable to the right PDP.
6.
Connect SPS B cable to the left PDP.
Turn SPS A and SPS B switches ON.
7.
Connect the power cables for the blade enclosure to the PDP.
8.
Connect the Control Station to the left PDP.
2
4
3
5
1
6
7
8
9
#