Installation Guide
Flatpack2 -48V 150A
~ 2029242 R2, May 2008
29
9.
Startup Checklists
This section includes basic checklists to assist the user in verifying proper
installation and starting system operation.
Pre-Start Check
Power is OFF
CHECK THE FOLLOWING POINTS
:
OK
1.
Flatpack2 system installation is completed; The
Flatpack2 Installation Check List
is filled in.
All cabling is securely terminated with
correct polarity
2.
All battery and load Breakers / fuses are disconnected
3.
AC input cable(s) and AC earth wire (Ground) are terminated
4.
Site specific parameters and settings are known
5.
AC supply and all Breakers / fuses are switched OFF
Start-up, No-Load & Load Adjustments
Power is ON
CARRY OUT FOLLOWING
:
OK
1.
Install all rectifier modules in desired locations
2.
Verify AC input voltage is correct;
Measure and verify
3.
Switch ON the external AC feeds
4.
Verify all rectifier modules are working, Green power LEDs are ON
Verify
5.
Verify The
Smartpack
is functioning Green power LED is ON
Verify
6.
Connect a PC to the PS system
Install the
PowerSuite
software, if required
7.
Verify DC output voltage;
Measure and adjust as needed
8.
Measure battery voltage, confirm level, and close disconnect if present Verify correct
polarity!
9.
Verify System Setup is in accordance with desired configuration
Enter site spec.
info in
PowerSuite
10.
Connect all load Breakers / fuses, and verify no alarms are displayed
11.
Verify the rectifiers output current, and load function
12.
Verify System Alarm Setup is in accordance with desired configuration Configure alarm
mapping in
PowerSuite
13.
Use PowerSuite to simulate Alarm Relay conditions
Verify all alarm
relays are
working correctly
14.
This completes the basic system start-up and configuration