Stage 5: Temperature and
moisture sensor’s
installation
The temperature and moisture sensor should be
installed in the installation tube after the sur-
face has been completed. Then, the sensor’s wire
should be fed into the protective conduit installed
before the surface has been completed, with the
so called “draw wire”. Under the sensor, the wire
excess should be deposited min. 1 ft (30 cm) for
the future sensor replacement, if required.
The sensor should be positioned approx. 0.2” (5 mm)
below the surface level to enable water deposition
on the sensor. After the sensor has been levelled, fill
the vacant space e.g. with concrete.
Stage 4: Finishing
surface works
During surface works, level the installation
tube, so that it is positioned 0.2” (5 mm) below
the level of the surface. Due to this, the water
will be deposited on the temperature and mois-
ture sensor.
Ground temperature and moisture sensor ETOG-56T with
installation tube (for soil, concrete flagstones, paving
cobbles etc.) can be used for heating control of drive-
ways, traffic routes, etc.