Assembly
5.2.2 Premises
The premises must meet the following requirements:
B
The installation location must comply with the effective
applicable laws and regulations for boiler rooms
(e.g. in Germany, the ordinance for heat-producing
appliances (Feuerstättenverordnung)).
B
The substrate on which the generation unit is to be
installed must be flat, even, solid, dry and load-bearing.
B
The ambient air temperature must be between
+5°C and +30°C.
B
The system must be protected against frost and the
elements.
The following are not permitted:
B
Installation on floating screed.
B
Operation of tumble dryers in the same room.
B
Storage of explosive or highly flammable materials
(e.g. paper, paints, petrol) within the installation
location.
B
Use of aggressive substances (e.g. sprays, solvents,
chlorinated cleaning agents, paints, adhesives) in the
vicinity of the system.
If the system is installed in vaulted cellars or bare smooth-
walled rooms (hard-walled), there is a risk of noise and
sound resonance.
The system must be positioned so that the following
requirements are fulfilled:
B
None of the system’s ventilation or extraction devices
may be blocked or closed.
B
The emergency stop switch must always be accessible.
Space requirement for VARION® C-POWER S
> 1000
> 1000
> 1000
> 1000
1226
1097
635
Space requirement for VARION® C-POWER M
1480
> 1000
> 1000
> 1000
> 1000
1097
643
1233
708
Space requirement for VARION® C-POWER M+
> 1000
> 1000
> 1000
> 1000
1659
1400
781
The minimum clearance to the generation unit (> 1,000 mm
on all sides) must be maintained.