E F A P O W E R E V - P C - I N S T A L L A T I O N A N D U S E R M A N U A L
15 | 37
5.3.4
ASSEMBLY INSTRUCTIONS / PLACING
This Unit was designed to be mounted on the wall. Nevertheless, with an external accessory can also be
anchored to the floor. The next chapters have the necessary information for both situations.
5.3.4.1
MOUNTING ON THE WALL
The EV-CW and EV-SW are prepared to be mounted on the wall.
In the following figures some details are shown regarding the drilling layout for the Unit.
Each unit must be installed by using 4 (four) M5 bolts. Length must comply with local codes. While a concrete
wall for installation is preferred, installation on a drywall will be acceptable if at least 2 anchors (13/64
’’ dia. (M
5)
lag screws) are in studs and if the remaining drywall anchors are heavy-duty.
Depending on the configuration of the EFAPOWER EV-PC, we have different cable entry points, which are
represented in the following two figures. The
cable entry shall respect
the
place
that was
assigned
to it (market
with green).
CE and GB MARKED UNITS:
▪
Cable gland
M40
:
AC input
(refer Chapters 5.3.4.3 and 5.3.4.4)
▪
Cable gland
M25
(for connections between central and satellite units):
communication cable
(refer to
Chapter 5.3.4.5)
Figure 10 - EFAPOWER EV-PC CE / GB Drilling and conduits Layout (rear view)