7.
Operation procedures
7.1.
Start up
Note:
The pump should be bled and filled with water
before start.
7.2. New system
In order to ensure a problem-free start up of a new
system the pipe system must be flushed and bled.
Bleeding the pipe system
1. Turn on the water supply to rinse and bleed the
entire system. If satellites are installed open the
tap furthest away until no air or dirt comes out.
Then rinse and bleed the next tap and continue
until the tap closest to you has been rinsed and
bled.
2. Mount satellites, if any
Bleeding the pump
3. Loosen the relief plug (A) 1-2 revolutions until
water and air begin to flow out.
Never loosen the relief plug while the pump
is running as this may damage the packing.
4. Tighten the relief plug again
5. Start the pump so that all remaining air pockets
are forced up to the top of the pump.
6. Stop the pump
7. Loosen the relief plug 1-2 revolutions again and
bleed the system until only water flows out.
8. Tighten the relief plug once more
The booster is now ready for operation.
Press “I” on the control panel.
7.2.1.
Long Stops
If long productions stops are planned (more than 6
months) and the pump is emptied of water, it is rec-
ommended that the pump be secured as follows:
1.
Remove the coupling safety guard.
2.
Spray a couple of drops of silicone oil onto
the axle between the top section and the
coupling.
6.7. Water Connection
• Before the unit is connected to the
water supply pipe, the supply line
should be rinsed carefully in order
to remove coarse impurities and
metal shavings.
• The connection for water must be
made at the top of the unit. (see
layout drawing).
• Minimum internal diameter of the
supply pipe must be at least 1 1/4”
external (ø36mm internal).
• The unit must be fitted with a clos-
ing valve for water on the inlet (see
drawing 110003601).
• The pressure loss in the supply line
must be held as low as possible by
- avoiding long supply pipes
- mounting low pressure resistance
ball valves and
- avoiding fittings with high pressure
loss.
• When installing the piping, take care
to avoid air traps.
• All pipe connections to the unit must
be screwed connections ensuring
simple maintenance and dismantling
of the station.
Max. allowed temperature of supply water: 70°C
Max. allowed pressure of supply water: 2-8 bar
For an optimum functioning we recom-
mend installing a filter on the inlet to
avoid impurities. Min. Filter mesh size
800µ -> 1500μ.
Содержание Hybrid-BF4
Страница 7: ......
Страница 64: ......
Страница 66: ...English EN 1 2 16 3 13 5 11 14 15 6 10 7 8 9 4 12 17 18 Pegasus P BW4 110008163 66 English EN...
Страница 68: ...English EN 3 12 5 4 14 1 10 11 2 13 6 7 9 15 8 16 Hybrid P BW7 110008164 68 English EN...
Страница 70: ...English EN Hybrid P BF4 Hybrid P BF8 110008165 5 6 7 1 2 2 8 3 4 70 English EN...
Страница 72: ...English EN Inlet pipe 1 6 5 3 3 2 7 8 110001270 4 110001406 72 English EN...
Страница 74: ...English EN Outlet pipe 6 2 3 1 3 5 4 7 8 110008166 74 English EN...
Страница 76: ...English EN 1 3 4 8 8 1 3 5 10 6 7 9 2 2 110008167 Hybrid P BF4 Hybrid P BF8 76 English EN...
Страница 78: ...English EN 1 2 7 3 3 5 6 4 110003710 Pipe holder system 78 English EN...
Страница 88: ...88 Fran ais FR Espa ol ES English EN Deutsch DE Installation 110003609 110008251...
Страница 91: ...91 Fran ais FR Espa ol ES English EN Deutsch DE Mounting Pegasus P BW4 110008170...
Страница 92: ...92 Fran ais FR Espa ol ES English EN Deutsch DE Mounting Hybrid BW7 110008171...
Страница 93: ......
Страница 94: ...Layout Pegasus Pegasus P BW4...
Страница 96: ...Hybrid P BW7 Layout Hybrid...
Страница 98: ...Hybrid P BF4 Layout Hybrid...
Страница 100: ...Hybrid P BF8 Layout Hybrid...
Страница 102: ...No 110008175A 08 2021 Serial no xxx 000XXX Printed in Denmark...