3.7
Verify the Installation
Check LED states to verify ONT status (Section 3
.7.1
).
Services are not available until the ONT is ranged and provisioned in the PON network. If services
must be verified at the time of installation, refer to Section 3
.7.2
for additional instructions.
3.7.1
Activating the ONT
Once the ONT installation is complete, follow the procedure below for verifying ONT status. Figures
below shows the typical status LED display after the ONT boot sequence is complete.
Figure 3 ONT has not yet been provisioned
Figure 4 ONT has already been provisioned
• Verify that the PWR LED light is green, indicating that local power level is good.
• Verify that the LINK LED light is green, indicating that the ONT is operating normally.
The ONT is placed into service remotely through the OLT. Services to the ONT are likewise
provisioned and turned up remotely through the PON network.
-
If the LINK LED lights green, indicating that the ONT is communicating with the PON network,
no further activation is necessary and you can proceed to Section 3
.7.2
: Verifying Services.
-
If the LINK LED does not light green, contact the NOC (Network Operation Center) to activate the
line. You may be required to provide or confirm the following information about the ONT: vendor,
model number, serial number. Once the ONT has been activated in the network, and the LINK
LED is lit green, you can proceed to Section 3
.7.2
: Verifying Services.