Disassembly and Assembly 

 
 
 
 
 
 

 
 
 

 

1.   Disassembly 

 

When disassembling pump, have a piece of 
cardboard or plywood ready to place the parts 
on as you work. Do not pile parts on top of each 
other. They should be laid out neatly in rows the 
"O" ring and gasket cannot be used again once 
they are removed. Have replacement parts 
ready. 

 

Disassemble In the following order, referring to 
the sectional view. 

 

Be sure to cut off power source before 
beginning disassembly. 

(1)   Drain all water from casing. 
(2)  Remove the motor from the common base. 

Inspect shaft coupling rubber and replace if 
excessively worn. 

(3)  Remove the casing cover bolts, and remove 

casing cover and shaft bearing frame from 
casing. You will now be able to inspect the 
inside of the pump. Check for wear and other 
abnormal signs. Replace casing ring when 
wear approaches 1 mm. 

(4)  Remove impeller nut (right hand thread) and 

impeller washer (some models do not have 
one), and remove impeller from casing. If the 
impeller is rusted and will not come loose, tap 
its end lightly with a wooden hammer to 
release. 

(5)  Remove the impeller key from the main shaft 

(some models do not have a key), the casing 
cover from the shaft bearing frame, and the 
deflector from the main shaft. 

   

Mechanical seal type:

 At this point in 

disassembly, the fixed portion of the 
mechanical seal is attached to the casing cover 
and the rotating portion to the main shaft. The 
fixed portion of the mechanical seal can be 
removed by pushing it out of the shaft hole in 
the casing cover with a screw driver of similar 
tool. 

   

Gland packing type

: Remove the packing 

gland from the casing cover and take out the 
packing and lantern ring bushing (some models 
do not have a lantern ring bushing). 

(6)  Remove the shaft bearing cover from the shaft-

bearing frame and take out the main shaft. 
Inspect condition of the shaft bearing and 
replace if it does not rotate smoothly. 

 
 
 
 
 
 

 
 
 
 
 
 
 
 

 
 
 
 
 
2.   Assembly 

Re-assemble in reverse order of disassembly.  
Re-assemble of following points. 
(1)  Gland packing type: Replace gland packing 

with new packing, shifting joints 180° until 
last joint is on the bottom. 

Mechanical seal type: Wipe contacting part of 

mechanical seal with a dry cloth. 

(2)  Replace "O" ring with a new one. 
(3)  Replace all parts that are excessively worn or 

damaged. 

(4)  Tighten all bolts evenly. 

 
 

Please obtain "O" rings, gland packing and 
other parts from pump dealer. The table of 
dimensions is given in 

"Maintenance".

 

 

CAUTION

 

All Service should be done by factory trained or qualified personnel only. 
Be sure to cut off power source before beginning disassembly.

 

Содержание FSA

Страница 1: ...Volute Pump MODEL RQWHQWV 1 Safety Information and Introduction 1 2 Installation 2 3 Operation 4 4 Maintenance and Service 5 5 Replaceable Parts 6 6 Troubleshooting 7 7 Contruction 8 8 Disassembly an...

Страница 2: ...16 3 kgf cm2 for standard flange JIS 16K RF Synchronous Speed 3000 min 1 1500 min 1 Installation Indoors Outdoors Impeller Enclosed Shaft seal Mechanical seal Gland Packing Sealing Self flushing Exte...

Страница 3: ...ad of expelling it 4 To reduce effect of water hammer install such a device as a quick closing check valve 5 Suction system 1 The end of the suction piping should be submerged to a depth of at least t...

Страница 4: ...Wiring 1 Refer to Fig 3 for correct wiring It is important that wiring be correct and that motor is properly grounded 2 Check the following points before turning on operation switch 1 Is the fuse the...

Страница 5: ...ing 2 Operation CAUTION Check rotation Correct rotation is clockwise when viewed from top of motor Pump should be started with gate valve closed then the operator should open the valve gradually 1 Clo...

Страница 6: ...bration may be due to conditions such as 15 incorrect centering defective piping or loose foundation bolts Inspect carefully In the event that special vibration control measures are necessary EBARA ha...

Страница 7: ...5 FSKA FH 35 Gs 335 51x35x8 4 6307 ZZ 100x65 FSKA EA 262 40 Gs 335 56x40x8 4 6208 ZZ 100x80 FSGA FH 25 Gs 275 41x25x8 6305 ZZ 100x80 FSHA Gs 225 100x80 FSJA FH 35 Gs 275 100x80 FSGCA Gs 185 100x80 FSH...

Страница 8: ...ion 3 Air pocket in suction piping 4 Suction height too high for pump 1 Prime sufficiently 2 Inspect repair suction piping shaft sealing 3 Reinstall piping 4 Re examine original plan Overloads over cu...

Страница 9: ...oil Spring 111 1 Spring Holder Stainless Steel 1 No Part Name Material Qty 119 Gland Packing 4 or 5 091 Gland 085 Lantern Ring Bushing Bronze 1 No Part Name Material Qty 207 Plug Steel 111 Mechanical...

Страница 10: ...rame and the deflector from the main shaft Mechanical seal type At this point in disassembly the fixed portion of the mechanical seal is attached to the casing cover and the rotating portion to the ma...

Страница 11: ...10 MEMO...

Отзывы: