8. Degrease the upper side of the lead sheath and sand it
lightly, for example, with a Scotch Brite scouring pad.
Apply a couple of layers of polyethylene tape to the lead
sheath, so that the diameter measured across the tape
equals the inside diameter of the plastic entry bushing,
see figure 4.
Make sure that the upper side of the tape is flush with
that of the lead sheath (see arrow).
Smooth out any wrinkles.
9.
Slide the cable box on to the cable terminal block of the
panel.
Pull the cable next to the cable box until the polyethylene
tape protrudes about 15 mm beneath the plastic entry
bushing.
Mark the cable just above the cable clamp, see figure 5.
10. Remove the cable box from the cable terminal block.
11.
Remove the plastic entry bushing from the cable box and
slide it over the cable.
Then, if applicable, fix the crimp cable sockets on the
aluminium cable.
In this case, skip step 14.
12. Slide the cable box over the cable and then over the plastic
entry bushing, see figure 6.
4.
5.
6.
Содержание SVS/12
Страница 133: ...SVS 12 994 530 G01 02 133 9 2 Voltage detecting system Wega 1 2...
Страница 134: ...SVS 12 134 994 530 G01 02...
Страница 135: ...SVS 12 994 530 G01 02 135...
Страница 136: ...SVS 12 136 994 530 G01 02...
Страница 137: ...SVS 12 994 530 G01 02 137 9 3 Phase monitor Orion 3 0...
Страница 138: ...SVS 12 138 994 530 G01 02...