Enterprise Power Solutions Installation and Operation Guide
14
Copyright © 2008 Eaton Corporation. All Rights Reserved.
IPN 997-00012-56C September 2008
Installation Tasks
Before starting the installation, review the following information:
•
Required Equipment and Tools on page
•
Warnings and Cautions on page
•
Inspecting the Equipment and Reporting Damage on page
Complete the Installation tasks in the following order:
Task Description
Reference
1
Check the AC Supply
2
Customize the EPS2/EPS5
3
Mount the EPS2/EPS5 in the Rack
4
Connect the Output Cables
See details on page
5
Install the Batteries Modules (if required)
6
Mount the Battery Temperature Sensor (if required)
7
Connect communications cable (if required)
8
Connect to the AC Supply Point
See details on page
For details of external communications refer to Communications Options in the System
Controller Operation Handbook (see Related Information on page
).
Task 1 - Check the AC Supply
It is important that the ac supply for the Enterprise Power Solutions dc power system
includes the correct levels of protection.
Step 1 - Check the type of ac supply
Check the type of ac supply. Only the types of ac supply listed in the
Specifications on page
are suitable for the EPS2/EPS5.
Only use an ac supply referenced to ground, or with a protection system so
that the phase-ground voltage cannot exceed the rating of the rectifier.