Parallel Communication
64
Eaton 9355 UPS (20/30kVA) Installation and Operation Manual 164201626—Rev F
www.eaton.com/powerquality
4.
Set the jumper pins on the Powerware Hot Sync CAN Bridge Card according to the parallel configuration
(see Figure 49):
l
If only two UPSs are paralleled, then set both cards to Pins 1 and 2.
l
For three or four paralleled UPSs, set the cards of the first and last UPSs to Pins 1 and 2; set the cards for
the middle UPSs to Pins 2 and 3.
Figure 49. Setting the CAN Bridge Card Jumper J7 (Side View)
5.
Install the CAN Bridge Card into X-Slot 2 (see Figure 36 and Figure 51).
6.
Strip shielded, four-wire, twisted-pair wire (maximum 18 AWG recommended) for CAN Bridge Card wiring
and pull-chain wiring.
7.
Repeat Steps 1 through 6 for each UPS.
8.
Route the wiring through the conduit from the communication wiring access plate to the opening
between the two X-Slot communication bays on each UPS (see Figure 50).
Figure 50. Routing the Cables
Communication
W
iring Access Plate
Содержание Powerware 9355
Страница 1: ...Eaton 9355 UPS 20 30 kVA Installation and Operation Manual...
Страница 2: ......
Страница 3: ...Eaton 9355 UPS 20 30 kVA Installation and Operation Manual...
Страница 99: ......
Страница 100: ...164201626 D 164201626 F...