Installation Instructions for the Walking Beam

Interlock for PD4 Circuit Breakers and Molded  

Case Switches

EATON 

www.eaton.com

IL012380EN

WARNING

DO NOT ATTEMPT TO INSTALL OR PERFORM 
MAINTENANCE ON EQUIPMENT WHILE IT IS 
ENERGIZED. DEATH, SEVERE PERSONAL INJURY, OR 
SUBSTANTIAL PROPERTY DAMAGE CAN RESULT 
FROM CONTACT WITH ENERGIZED EQUIPMENT. 
ALWAYS VERIFY THAT NO VOLTAGE IS PRESENT 
BEFORE PROCEEDING WITH THE TASK, AND ALWAYS
FOLLOW GENERALLY ACCEPTED SAFETY 
PROCEDURES.

EATON IS NOT LIABLE FOR THE MISAPPLICATION OR 
MISINSTALLATION OF ITS PRODUCTS.

 

When the walking beam interlock is used, the wiring troughs in 

the back of each circuit breaker base are blocked by the plungers 

and cannot be used for opposite side-exiting accesory pigtail leads.

This instruction leaflet (IL) gives detailed procedures for installing 

the walking beam interlock.

The walking beam interlock must be mounted before the circuit

breakers are connected to an electrical system. Installation 

consists of drilling mounting panel to accept circuit breakers and 

walking beam assembly; securing circuit breakers to mounting 

surface and; installing walking beam. To install the walking beam 

interlock, perform the following steps:

2. INSTALLATION

The user is cautioned to observe all recommendations,warnings, 

and cautions relating to the safety of personnel and equipment, as

 

well as all general and local health and safety lawscodes, and 

procedures.

The recommendations and information contained herein are based 

on Eaton experience and judgement, but should not be considered 

to be all-inclusive or covering every application or circumstance 

which may arise. If any questions arise, contact Eaton for further 

information or instructions.

1.

 

INTRODUCTION

General Information

The walking beam interlock (Fig.1-1) provides mechanical 

interlocking between two adjacent circuit breakers of the same 

pole configuration to prevent both circuit breakers from being 

switched on at the same time. The walking beam interlock 

assembly is bolted to the rear of a customer-supplied mounting

 

panel.The circuit breakers are then secured to the mounting 

panel. Plungers are inserted through access holes in the 

mounting panel and base of each circuit breaker. The plungers 

are then attached to each end of the beam assembly. 

Adjustment of the walking beam assembly is necessary for the 

panel thickness being used. Customer-supplied mounting panels 

from .25 to1.00 in.(3.18 to 25.40 mm) can be used with the 

walking beam interlock.

Fig. 1-1 Walking Beam Interlock Installed Between Two 3-pole 

PD4 Circuit Breakers.

Note: Factory modified circuit breakers must be ordered to install 
the walking beam interlock.

Содержание Power Defense

Страница 1: ...1 Introduction 2 2 Installation 2 3 Adjustment 3 Instruction Leaflet IL012380EN Installation Instructions for the Walking Beam Interlock for PD4 Circuit Breakers and Molded Case Switches Effective Oc...

Страница 2: ...NSTALLATION The user is cautioned to observe all recommendations warnings and cautions relating to the safety of personnel and equipment as well as all general and local health and safety lawscodes an...

Страница 3: ...ing panel and circuit breaker Fig 2 5 2 2 Predrill circuit breaker mounting panel Fig 2 2 PD4 2 and 3 pole and Fig 2 3 PD4 4 pole show mounting panel hole sizes and dimensions for the breaker configur...

Страница 4: ...ffective October 2020 Installation Instructions for the Walking Beam Interlock for PD4 Circuit Breakers and Molded Case Switches IL012380EN 3 5 Carry out a functional check as follows b Open one circu...

Страница 5: ...ock for PD4 Circuit Breakers and Molded Case Switches Instruction Leaflet Effective October 2020 IL012380EN Drill Hole per Fig 2 1 2 Places 313 7 95 DIA 12 Places 625 15 88 Dia Hole 2 Places LOAD END...

Страница 6: ...Mounting Bracket Plungers and Long Cotter Pins Installed L Frame 4 pole Circuit Breaker Arrangement Shown Plungers Installation Instructions for the Walking Beam Interlock for PD4 Circuit Breakers an...

Страница 7: ...7 EATON www eaton com Notes Installation Instructions for the Walking Beam Interlock for PD4 Circuit Breakers and Molded Case Switches Instruction Leaflet Effective October 2020 IL012380EN...

Страница 8: ...ature is subject to the terms and conditions outlined in appropriate Eaton selling policies or other contractual agreement between the parties This literature is not intended to and does not enlarge o...

Отзывы: