1. This product should be installed, commissioned and maintained by or under the supervision of a competent electrician in                    
accordance with current electrical engineering Codes of Practice, Requirements for the Electrical Installations (IET Wiring 
Regulations BS7671), Construction (Design and Management) Regulations, HSG150 - Health and Safety in Construction, Statutory 
requirements and any Specific instruction issued by the Company. 
2. After completing the installation and testing of this product it is essential that this leaflet is drawn to the attention of the 
person responsible for its future operation and maintenance, and is at all times available for ready reference. 
3. These notes assume throughout that the product is disconnected from the supply. It is essential that this is done before any   
work is carried out. 
4. These Panelboards are only designed for use with Eaton MCCBs. Failure to comply will result in invalid warranty and 
certification. 

Items supplied with Surge Protection Modules 

M5 x 12mm self tapping screw  

  4 Qty 

Cable Tie 

 

  4 Qty 

Cable Tie Base 

 

  2 Qty 

92mm x 92mm window 

   1 Qty 

 

25mm²  M8 Ring Connector 

   1 Qty 

25mm²  Cable Ferrules  

   4 Qty 

25mm²  Cables    

   5 Qty 

Grommet 25mm diameter 

   1 Qty 

Surge Supression Device Label 

   1 Qty 

BEFORE INSTALLATION: 

A. Verify that the system is wired in a Three Phase Star configuration (fig. 5) and that the voltage rating of the system matches 
the voltage rating of the SPD as shown on the label.  
If the Neutral to Earth voltage is greater than 5 VAC, then a problem may exist in the electrical system. The SPD may be installed; 
however, a qualified person should be consulted to correct the problem. 
B. The SPD must be connected to the Panelboard via a 4 Pole 63A MCCB and adaptor. If the board is compartmentalised then the 
appropriate compartment kit is required to segregate the 4 Pole MCCB. (needs to be ordered separately) 

SPD MOUNTING POSITION 

There are two positions for the SPD.  
Position 1 is in the panel board (fig .1 & 2) and Position 2 is in 
the cable way (fig.3 & 4).  
1. As standard the SPD is mounted in the panel board on the 
RH side for the shortest possible wire installation. The 4 Pole 
NZM1 must be fitted on the FIRST outgoing way to minimise 
the connecting wire lengths.  
The SPD status indicators can be viewed through the window 
in the inner cover and an auxiliary contact is provided for 
external monitoring.  

 