![Eaton Cutler-Hammer J-Frame Series Скачать руководство пользователя страница 5](http://html1.mh-extra.com/html/eaton/cutler-hammer-j-frame-series/cutler-hammer-j-frame-series_instructions-for-installation-manual_4020632005.webp)
I.L. 29C211E
Effective 04/04
are positioned correctly in the line end cover
mounting holes
2-6. Using the hardware provided with the solenoid
operator, shown in Figure 2-2 and Table 2.1,
loosely fasten the line end of the solenoid opera-
tor in place DO NOT TIGHTEN.
2-7.
Install the mounting hardware, shown in Figure 2-
2 and Table 2.1, into the load end by lifting the
solenoid operator up enough to start the screws in
the top of the special threaded stacking screws.
Imperial
1 Screw, stacking, special, Imperial male thread
2 .250-20 x 1.00 Filister Head Screw and Lockwasher
Metric
1 Screw, stacking, special, Metric male thread
2 M6-0.7 x 25.4 Filister Head Screw and Lockwasher
Table 2.1 Electrical Operator Mounting Hardware
Page 5
Figuer 2-2A Electrical Operator Mounting Hardware (see Table 2.1) K-Frame
Содержание Cutler-Hammer J-Frame Series
Страница 10: ...I L 29C211E Fig 5 2 Electrical Solenoid Opertor Mounted on 3 Pole J Frame Breaker Effective 04 04 Page 10...
Страница 11: ...I L 29C211E Effective 04 04 Page 11 NOTES...
Страница 12: ...I L 29C211E Pittsburgh Pennsylvania U S A Effective 04 04 Style 6631C42H06 Printed in U S A TQC NOTES...