78
Eaton 93PM Integrated Accessory Cabinet-Tie (50 kW and 100 kW IAC-T) Installation and Operation Manual P-164000371—Rev 05
Figure 43. Eaton 93PM 50 kW IAC-T and 93PM 100 kW IAC-T Schematic – Four MOBs with MIS and MBP
MBP
MOB1
MOB2
TO LOAD/DISTRIBUTION
FROM UPS1 OUTPUT
BYPASS INPUT
TIE BUS A
6
5
7
1
8
TB1
MOB3
[4+0]
[3+1]
10
9
11
2
12
14
13
15
3
16
18
17
19
4
20
2
1
3
5
4
6
8
7
TB2
MOB1 NC -- UPS1 BLDG ALARM
MOB1 COM -- UPS1 BLDG ALARM
MOB1 NO -- UPS1 PULL CHAIN
MOB1 GND -- UPS1 PULL CHAIN
MBP COM -- UPS1 MBS_GND
MBP NC -- UPS1 MBS_DET
MBP COM -- UPS2 MBS_GND
MBP NC -- UPS2 MBS_DET
MBP COM -- UPS3 MBS_GND
MBP NC -- UPS3 MBS_DET
MBP COM -- UPS4 MBS_GND
MBP NC -- UPS4 MBS_DET
MOB2 NC -- UPS2 BLDG ALARM
MOB2 COM -- UPS2 BLDG ALARM
MOB2 NO -- UPS2 PULL CHAIN
MOB2 GND -- UPS2 PULL CHAIN
MOB3 NC -- UPS3 BLDG ALARM
MOB3 COM -- UPS3 BLDG ALARM
MOB3 NO -- UPS3 PULL CHAIN
MOB3 GND -- UPS3 PULL CHAIN
MOB4 NC -- UPS4 BLDG ALARM
MOB4 COM -- UPS4 BLDG ALARM
MOB4 NO -- UPS4 PULL CHAIN
MOB4 GND -- UPS4 PULL CHAIN
MOB4
FROM UPS2 OUTPUT
FROM UPS3 OUTPUT
FROM UPS4 OUTPUT
TB1
TB1
TB1
TIE BUS B
TIE BUS C
[3+1]
[4+0]
[3+1]
[4+0]
MIS
[4+0]
[3+1]
LOAD BUS A
LOAD BUS B
LOAD BUS C
FROM UPS1 GROUND
FROM UPS2 GROUND
TO LOAD GROUND
FROM BUILDING GROUND
G
G
G
G
TBG
G
G
FROM UPS3 GROUND
FROM UPS4 GROUND
Содержание 93PM IAC-T Series
Страница 98: ...P 16400037105 P 164000371 05 ...