background image

 

-6- 

 

Fig. 2.3.2 3U 1.5KVA-3KVA rack rear panel 

Description of rear panel   

a)  Fan and fan guard 

b)  Output power supply socket 

c)  AC over-current protector 

d)  IEC Input socket 

e)  Communication interface (standard configuration USB+RJ45) 

f)  SNMP card slot 

g)  External battery connector 

2.4    Product installation instructions 

2.4.1 Installation attentions 

1.  Put UPS in a well-ventilated place and ensure the heat emission holes and fan 

peripherals  of  the  chassis  meet  the  ventilation  conditions  at  a  distance  of 

150mm above and keep away from water, combustible gases and corrosives.   

2.  Turn  off  the  devices  which  need  uninterrupted  power  supply  (such  as  host   

computer), disconnect the power cord from the utility power socket and connect 

it  to  the  output  socket  of  UPS  connect  the  devices  which  do  not  need  to  be 

connected with UPS to the common utility power socket. 

3.  Put UPS input plug into the utility power socket (ensure the zero wire and live 

wire are correct and the ground wire is good).   

4.  The ambient temperature of UPS shall be kept between 0

 and 40

 

 

-7- 

5.  It is recommended to charge the battery for  8  hours  before  using  it.  UPS  will 

charge  the  battery  automatically  as  long  as  the  input  utility  power  meeting 

requirements is connected to the host. 

6.  For the extended runtime model,  connect  the  battery  first  after  confirming  the 

battery wires, and then connect the utility power line. 

15cm

OF F

ON

TEST /MUTE

15cm

       

 

Fig. 2.4.1 Installation attentions 

2.4.2 Battery installation attentions for extended runtime model 

Warning: 

In  order  to  ensure  the  safety  of  equipment  and  personnel,  theinstallation  must  be 

carried out by professionals. 

1.  First connect the battery bank with accompanied battery connecting wires (note 

the  red  wire  shall  be  connected  to  the  anode,  and  the  black  wire  shall  be 

connected to the cathode).     

2.  Confirm  the  connection  of  the  battery  bank.  Measure  the  identification  of  the 

battery input  socket  and  the  positive  and  negative  of  battery  wire  terminals  of 

UPS  with  a  multimeter.  The  voltage  shall  be  consistent  with  UPS’s  input  DC 

voltage. 

3.  Be sure to check whether the installation is correct or not after it is completed. 

 

Fig. 2.4.2 Schematic diagram of DC24V tower battery connection 

Содержание EA610

Страница 1: ......

Страница 2: ......

Страница 3: ...or low above 40 or below 0 and the humidity is high above 90 4 The place having direct sun exposure or close to heating equipment 5 The place where violent vibration occurs 6 Outdoor 3 In case of fire...

Страница 4: ...ials of the machine for convenience of future handling The series of products are very heavy which shall be handled with care 2 1 2 Check whether UPS is damaged during the transportation If any damage...

Страница 5: ...erature of UPS shall be kept between 0 and 40 7 5 It is recommended to charge the battery for 8 hours before using it UPS will charge the battery automatically as long as the input utility power meeti...

Страница 6: ...ery automatically as long as it is connected to the utility power line 3 Installation of rack UPS 9 Vertical installation Combine the connecting extensions and RT foot pieces among the accessories int...

Страница 7: ...1 Press momentarily to enable inverter mute 2 In the utility power mode press momentarily to enable the battery discharge testing for 15 seconds 1 Press the key for 5 seconds to enter the setting int...

Страница 8: ...ery failure utility power failure 13 3 3 LCD display functions Rack LCD Tower LCD Graphics load and battery capacity display area 1 Each grid of the load and battery capacity display area 25 capacity...

Страница 9: ...el shutdown combination button for 3 seconds UPS will enter standby mode rack or bypass mode tower The yellow bypass indicator goes on Then cut off the utility power supply to shut down UPS Shutdown w...

Страница 10: ...5 3 Boost charge voltage 17 1 The left figure shows the boost charge voltage interface of rack UPS and the right figure shows the boost charge voltage interface of tower UPS 2 Press the function setti...

Страница 11: ...ging current is 1A for standard model and 10A for extended runtime model by default 3 After selecting Confirm press the key momentarily to save the interface by reference to save and exit setting Pres...

Страница 12: ...elect ON or OFF the DC self starting function is off by default 3 After selecting Confirm press the key momentarily to save the interface by reference to save and exit setting Press the key or momenta...

Страница 13: ...to exit the state of automatic page up down 1 Output Display UPS output voltage and output frequency as shown below the left figure shows the display interface of rack UPS and the right figure shows...

Страница 14: ...shutdown It can be set 3 load to shut down after 80s transfer time 10ms THDV resistive load 5 Inductive load Yes Capacitive load Yes Resistive load Yes Protection Overload short circuit battery low v...

Страница 15: ...collected too much dust or not 4 Check whether the input output and battery cables are firm or not and whether the cable insulation is good or not 5 Ensure UPS is well protected against moisture 6 St...

Страница 16: ...battery terminals are firmly fastened 29 9 Exception Handing Carry out the self checking according to the following methods in case of abnormal conditions If the abnormal condition cannot be eliminat...

Отзывы: